TREX SIGNATURE ® HORIZONTAL MESH RAILING Installation Instructions
HOW TO INSTALL MESH TRADITIONAL RAILING TREX SIGNATURE ®
13. Installing Top Rail onto Mesh Panel See instructions on page 8. 14. Attaching L-Brackets to Top and Bottom Rails See instructions on page 9. 15. Attaching Top Rail to Brackets See instructions on page 9. 16. Installing Snap-in Channel Filler See instructions on page 10. NOTE: Top Bracket Covers are not attached in this configuration. Attaching 2 x 4 to Top Rail
17
Important: Only use with Pressure-treated post, Trex Post Mounts or Trex Joist Mount Post WITH Trex post sleeves. Trex Signature Posts and Joist Mount Posts cannot be used with Mesh Traditional. 1. Installing Posts, Post Sleeves, and Skirts See instructions on page 11 for pressure treated posts. Refer to detailed Trex Post Mount instructions if using these. Post and Post Sleeves are NOT CUT in this installation. 2. How to Measure Bottom and Top Rails See instructions on page 5. 3. Cutting Rails See instructions on page 5. 4. Attachment of Foot Block (REQUIRED) See instructions on page 5. 5. Installing Bottom Rail and Adding Weep Holes to Bottom Rail See instructions on page 6. 6. Cutting Mesh (if required) See instructions on page 6. 7. Cutting Bottom PVC Gasket and Installing onto Mesh See instructions on page 6. 8. Centering Mesh and Installing into Bottom Rail See instructions on page 7. 9. Installing Vertical PVC Gaskets into Mesh See instructions on page 7. 10. Installing L-Brackets into Vertical Supports See instructions on page 7. 11. Installing Vertical Supports See instructions on page 8. 12. . Cutting Top PVC Gasket and Installing onto Mesh See instructions on page 8.
18
17. Measure between posts and cut 2 x 4 to length. 18. P lace 2 x 4 on Trex Signature top rail. 19. Secure 2 x 4 to top rail
19
using Trex Signature Cocktail Bracket (sold separately). Ensure that there is a bracket at each end of the railing section, then space brackets
approximately every 24" and attach with 4 screws provided. NOTE: Pre-drilling before attachment is recommended. 20.Pre-drill and toenail 2-1/2"
20
(6.4 cm) approved deck screw at each end of 2 x 4 into post on back side of rail (side not facing decking). Bottom Bracket Covers and Caps See instructions on page 10.
21. Attachment of
12
Have Questions? 1–800–BUY–TREX
NOTE: Construction methods are always improving. Please ensure you have the most up-to-date installation instructions by visiting: trex.com
TR-SIGNATUREMP-0125