3.4 Positioning Your System for Use The position you select for the final site location should be in an area that allows the system to be accessible from all sides. Users must have unobstructed access to the power sources for the system and all associated system components and accessories. The final site location should be in a well-ventilated, preferably air con- ditioned room free of dust, debris, oils, etc. A temperature controlled laboratory environment is recommended.
Crane Method Use a crane to lift the upright test frame from the crosshead. If this method is used, Starrett strongly recommends using certified riggers experienced in moving heavy industrial equipment.
The final site location must be away from any machinery or equipment that can emit electromagnetic interference.
The final site location must be away from any machinery or equipment that can cause excessive vibration such as pumps, generators, etc.
Use an approved safety hooks with appropriate load capacity before attempting to lift test frame. Hook load capacity should be 2X the weight of the test frame.
If you have questions about the suitability of a location prior to installa- tion, contact your Starrett representative for assistance.
Use an approved safety strap with appropriate load capacity before attempting to lift test frame. Strap’s load capacity should be 2X the weight of the test frame.
Place protective padding around top plate.
IMPORTANT Place protective padding around crosshead. Make sure lifting hook and strap have a load capacity greater than 2X the weight of the test frame. Guide and balance the test frame as you lift it very slowly.
Place protective padding around crosshead.
Position test frame, then lower very slowly.
Guide the bottom of the test frame to prohibit “swinging”.
Lifting the MMD/FMD Series using a crane