CHIMNEY PROJECTS

Project 100M single flue concrete chimney repairs and installation of temporary bypass stack

Project Steel chimney refurbishment

Project Concrete chimney refurbishment

Client Hope Construction Material

Client Drax Generation Enterprise Ltd

Client Petroineos

Location Derby

Location Shoreham

Location Grangemouth

Hope Construction Materials appointed Zenith to install a temporary by-pass steel stack braced to the concrete chimney windshield to enable internal brickworks to be carried out, whilst allowing the plant to continue operation.

As part of the project, Zenith replaced the external access platforms and ladders. This included the full circumferential platforms at the 50m and 95m levels. We also installed previously removed access ladders and rest platforms from the 29m to 95m level. To gain access, we used suspended access cradles and a full circumferential suspended temporary works platform.

The BI601 chimney is a 61-meter concrete stack with refractory brick lining located in the COD2 Unit. Our project involved mobilizing skilled workers, specialized equipment, and materials to carry out the necessary refurbishment work.