Alaska Miner Journal, August 2023

Livengood Gold Project in Alaska’s Golden Heart

• Updated Pre-Feasibility Study (PFS) in November 2021 and T echnical R eport S ummary in 2022 • Mineral resource: 13.6m oz gold at 0.60 g/t. • Gold production: 6.4m oz for 20-year Life of Mine (LOM), annual 317,000 oz. • CAPEX $1.93B, Sustaining Capital $658m.

• All-in Sustaining Costs (AISC) years 1-5 $1,038/oz, LOM $1,171/oz. • Direct employment: 800 construction jobs, 331 production jobs.

or futu Livengood Gold Project: highly levered to the gold price with the opportunity to become a successful Alaska gold mine for decades to come. We will continue to prepare for future potential permitting and construction, while also conducting baseline environmental studies.