LFN Open House Boards

LYTTON FIRST NATION NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS

System Improvements. The Federal Government is funding each of these projects separately through Indigenous Services Canada, Community Infrastructure. The Stein Water System currently does not have capacity to service the proposed Nuuautin IR 2B Subdivision. The upgrade will provide increased water capacity to the LFN community currently connected to the Stein Water System. This upgrade to the system will service the new subdivision, address existing and future capacity concerns, and increase the reliability of the existing system, ensuring long term sustainability and community safety.

Welcome to the Community Open House for the Lytton First Nation (LFN) Nuuautin IR 2B Subdivision and Stein Water System Improvement Projects. Thank you for taking the time to review the project information material. Updated information about the projects can be found on the open house boards. We welcome your comments, questions, and feedback. As part of the recovery efforts following the Lytton Creek Wildfire, 39 temporary modular homes were constructed on Inkluckcheen IR 21 and Nuuautin IR 2 in 2022, along with a new community centre and band office. Additional homes are still needed, and it is a significant priority for LFN to build more homes for community members that are still without housing. LFN has contracted Aplin Martin to design a 28-Home Subdivision and the Stein Water

NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS WWW.APLINMARTIN.COM/LFNSUBDIVISION WWW.APLINMARTIN.COM/LFNWATERSYSTEM

NUUAUTIN IR 2B SUBDIVISION PROJECT SUMMARY In 2023 the subdivision project was initiated through funding from Indigenous Services Canada. In Winter 2024, Aplin Martin was selected to complete the subdivision design and water system improvement design, and prepare the tender package for In 2023 the subdivision project was initiated through funding from Indigenous Services Canada. In Winter 2024, Aplin Martin was selected to complete the subdivision design and water system improvement design, and prepare the tender package for In 2023 the subdivision project was initiated through funding from Indigenous Services Canada. In Winter 2024, Aplin Martin was selected to complete the subdivision design and water system improvement design, and prepare the tender package for construction. A 56-lot subdivision design has been completed, and 28 homes will be constructed in the subdivision. To ensure safe and reliable access to the site, Alkali Road will receive a full upgrade including full width asphalt surfacing, gravel shoulders, and drainage provisions. construction. A 56-lot subdivision design has been completed, and 28 homes will be constructed in the subdivision in 2025. To ensure safe and reliable access to the site, Alkali Road will receive a full upgrade including full width asphalt surfacing, gravel shoulders, and drainage provisions. construction. A 56-lot subdivision design has been completed, and 28 homes will be constructed in the subdivision in 2025. To ensure safe and reliable access to the site, Alkali Road will receive a full upgrade including full width asphalt surfacing, gravel shoulders, and drainage provisions. construction. A 56-lot subdivision design has been completed, and 28 homes will be constructed in the subdivision in 2025. To ensure safe and reliable access to the site, Alkali Road will receive a full upgrade including full width asphalt surfacing, gravel shoulders, and drainage provisions. NUUAUTIN IR 2B SUBDIVISION PROJECT SUMMARY NUUAUTIN IR 2B SUBDIVISION PROJECT SUMMARY In 2023 the subdivision project was initiated through funding from Indigenous Services Canada. In Winter 2024, Aplin Martin was selected to complete the subdivision design and water system improvement design, and prepare the tender package for

WATER SYSTEM IMPROVEMENT PROJECT SUMMARY WATER SYSTEM IMPROVEMENT PROJECT SUMMARY WATER SYSTEM IMPROVEMENT PROJECT SUMMARY A significant portion of LFN reserve land receives domestic water and fire protection from the Stein Water System. The water system draws water from the Stein River, treats this water, and delivers it across a vast area of LFN reserves on the west and east sides of the Fraser River. Prior to the wildfire, this water system was operating near capacity. With the addition of new development resulting from the wildfire recovery as well as the proposed new subdivision, the water system needs to be upgraded. River, treats this water, and delivers it across a vast area of LFN reserves on the west and east sides of the Fraser River. Prior to the wildfire, this water system was operating near capacity. With the addition of new development resulting from the wildfire recovery as well as the proposed new subdivision, the water system needs to be upgraded. River, treats this water, and delivers it across a vast area of LFN reserves on the west and east sides of the Fraser River. Prior to the wildfire, this water system was operating near capacity. With the addition of new development resulting from the wildfire recovery as well as the proposed new subdivision, the water system needs to be upgraded. River, treats this water, and delivers it across a vast area of LFN reserves on the west and east sides of the Fraser River. Prior to the wildfire, this water system was operating near capacity. With the addition of new development resulting from the wildfire recovery as well as the proposed new subdivision, the water system needs to be upgraded. A significant portion of LFN reserve land receives domestic water and fire protection from the Stein Water System. The water system draws water from the Stein A significant portion of LFN reserve land receives domestic water and fire protection from the Stein Water System. The water system draws water from the Stein A significant portion of LFN reserve land receives domestic water and fire protection from the Stein Water System. The water system draws water from the Stein

Key features for the 28 new homes are: Key features for the 28 new homes are: Key features for the 28 new homes are: Key features for the 28 new homes are:

The upgrades will include: The upgrades will include: The upgrades will include: The upgrades will include:

New underground water reservoir and new pump system to service the subdivision; New underground water reservoir and new pump system to service the subdivision; New underground water reservoir and new pump system to service the subdivision; New underground water reservoir and new pump system to service the subdivision; Upgrades to the existing water treatment system and pump stations; and Upgrades to the existing water treatment system and pump stations; and Upgrades to the existing water treatment system and pump stations; and Upgrades to the existing water treatment system and pump stations; and New water main connection to the subdivision, and tie-in to the existing system. New water main connection to the subdivision, and tie-in to the existing system. New water main connection to the subdivision, and tie-in to the existing system. New water main connection to the subdivision, and tie-in to the existing system.

On-site sanitary treatment (septic system); On-site sanitary treatment (septic system); On-site sanitary treatment (septic system); On-site sanitary treatment (septic system);

Snake fencing around each lot for safety; and Snake fencing around each lot for safety; and Snake fencing around each lot for safety; and Snake fencing around each lot for safety; and

Fire smart design safety features. Fire smart design safety features. Fire smart design safety features. Fire smart design safety features.

NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS WWW.APLINMARTIN.COM/LFNSUBDIVISION WWW.APLINMARTIN.COM/LFNWATERSYSTEM NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS WWW.APLINMARTIN.COM/LFNSUBDIVISION WWW.APLINMARTIN.COM/LFNWATERSYSTEM NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS WWW.APLINMARTIN.COM/LFNSUBDIVISION WWW.APLINMARTIN.COM/LFNWATERSYSTEM NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS WWW.APLINMARTIN.COM/LFNSUBDIVISION WWW.APLINMARTIN.COM/LFNWATERSYSTEM

STEIN WATER SYSTEM UPGRADES

0

400

800

Meters

NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS WWW.APLINMARTIN.COM/LFNSUBDIVISION WWW.APLINMARTIN.COM/LFNWATERSYSTEM

NUUAUTIN IR 2B SUBDIVISION: EXAMPLE RENDERINGS

FIG 1: LOT 34 FRONT VIEW

FIG 3: INTERSECTION VIEW

1

2

3

FIG 2: LOT 41 BACK VIEW

FIG 4: LOT 50 FRONT VIEW

4

NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS WWW.APLINMARTIN.COM/LFNSUBDIVISION WWW.APLINMARTIN.COM/LFNWATERSYSTEM

INDIGENOUS SERVICES CANADA (ISC) FUNDING PROGRAM

FAR (Feasibility Application Request): This application is made during the initial planning stage. This funding enables feasibility studies to be conducted to assess the project’s viability. Indigenous communities and/or organizations who are seeking funding for capital projects through ISC must adhere to structured funding programs. The FAR, DAR, and PAR are applications paired with cost estimate reports to request funding at different stages of a project.

DAR (Design Application Request): This application is made to initiate the design phase once the project is deemed feasible. This funding enables spending of funds necessary to complete the project design.

PAR (Project Application Request): This application is made to enable the construction phase. This funding enables the construction of the project, permitting the spending of the remaining project funds.

PROJECT TIMELINE:

September

March

March / April

PAR FUNDING SUBMISSION (Subdivision)

PRELIMINARY PAR FUNDING RESUBMISSION (for the Subdivision) Preliminary resubmission, SARA permit required prior to full approval.

PRELIMINARY PAR FUNDING SUBMISSION (for the Water System Improvement) Preliminary submission, SARA permit required prior to full approval.

2022-2023

DAR FUNDING SUBMISSION AND APPROVAL

July

DAR FUNDING APPROVAL

FUNDING

02

04

06

08

10

12

02

04

10

12

06

08

DELIVERABLES

DESIGN PHASE

May

August

January

Subdivision and Water System Improvement Pre-Design

Subdivision and Water System Improvement Design

Submission of SARA Permit Applications

CONSTRUCTION PHASE

CONSTRUCTION

September

Water System Construction Completion Target Winter

Summer

Water System Start of Construction Spring

Subdivision Start of Construction

Subdivision Construction Completion Target

NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS WWW.APLINMARTIN.COM/LFNSUBDIVISION WWW.APLINMARTIN.COM/LFNWATERSYSTEM

ents online at openhouse@aplinmartin.com

HOW CAN YOU PROVIDE INPUT? HOW CAN YOU PROVIDE INPUT? HOW CAN YOU PROVIDE INPUT? re posted online at www.aplinmartin.com/lfnsubdvision and ystem.

Please take an opportunity to review the boards around the room and engage the staff team with any questions or comments. We also encourage you to provide your feedback using any methods below: Please take an opportunity to review the boards around the room and engage the staff team with any questions or comments. We also encourage you to provide your feedback using any methods below: Please take an opportunity to review the boards around the room and engage the staff team with any questions or comments. We also encourage you to provide your feedback using any methods below: HOW CAN YOU PROVIDE INPUT? HOW CAN YOU PROVIDE INPUT?

ages

Write a comment on the form provided at this event (add to the drop box) Write a comment on the form provided at this event (add to the drop box) Please take an opportunity to review the boards around the room and engage the staff team with any questions or comments. We also encourage you to provide your feedback using any methods below: Please take an opportunity to review the boards around the room and engage the staff team with any questions or comments. We also encourage you to provide your feedback using any methods below:

Write a comment on the form provided at this event (add to the drop box)

Newsletter

Email us your comments online at openhouse@aplinmartin.com Email us your comments online at openhouse@aplinmartin.com Write a comment on the form provided at this event (add to the drop box) Write a comment on the form provided at this event (add to the drop box) Email us your comments online at openhouse@aplinmartin.com

Project questions and answers are posted online at www.aplinmartin.com/lfnsubdvision and www.aplinmartin.com/lfnwatersystem. Project questions and answers are posted online at www.aplinmartin.com/lfnsubdvision and www.aplinmartin.com/lfnwatersystem. Project questions and answers are posted online at www.aplinmartin.com/lfnsubdvision and www.aplinmartin.com/lfnwatersystem. Project questions and answers are posted online at www.aplinmartin.com/lfnsubdvision and www.aplinmartin.com/lfnwatersystem. Project updates can be found: Project updates can be found: Email us your comments online at openhouse@aplinmartin.com Email us your comments online at openhouse@aplinmartin.com Project questions and answers are posted online at www.aplinmartin.com/lfnsubdvision and www.aplinmartin.com/lfnwatersystem.

eetings

On the project webpages On the project webpages ase contact us. We will reply to all enquiries, comments, and questions. If m Council, it will be forwarded to Council by an administrator. At LFN Town Hall meetings At LFN Town Hall meetings Monthly in the LFN Newsletter Monthly in the LFN Newsletter orner of Lytton-Lillooet Highway (Highway 12), and Alkali Road. e Nuuautin IR 2B Subdivision and Water System Improvement Projects, cation where there will be water system upgrades, a subdivision plan, and ion. On the project webpages Monthly in the LFN Newsletter Monthly in the LFN Newsletter On the project webpages On the project webpages Project updates can be found: Project updates can be found: Project updates can be found: Monthly in the LFN Newsletter

If you have any additional question please contact us. We will reply to all enquiries, comments, and questions. If your feedback requires a response from Council, it will be forwarded to Council by an administrator. An Information Kiosk is located at the corner of Lytton-Lillooet Highway (Highway 12), and Alkali Road. The Kiosk includes information about: the Nuuautin IR 2B Subdivision and Water System Improvement Projects, the project partnerships, a map of the location where there will be water system upgrades, a subdivision plan, and emergency & other key contact information. An Information Kiosk is located at the corner of Lytton-Lillooet Highway (Highway 12), and Alkali Road. The Kiosk includes information about: the Nuuautin IR 2B Subdivision and Water System Improvement Projects, the project partnerships, a map of the location where there will be water system upgrades, a subdivision plan, and emergency & other key contact information. If you have any additional question please contact us. We will reply to all enquiries, comments, and questions. If your feedback requires a response from Council, it will be forwarded to Council by an administrator. An Information Kiosk is located at the corner of Lytton-Lillooet Highway (Highway 12), and Alkali Road. The Kiosk includes information about: the Nuuautin IR 2B Subdivision and Water System Improvement Projects, the project partnerships, a map of the location where there will be water system upgrades, a subdivision plan, and emergency & other key contact information. An Information Kiosk is located at the corner of Lytton-Lillooet Highway (Highway 12), and Alkali Road. The Kiosk includes information about: the Nuuautin IR 2B Subdivision and Water System Improvement Projects, the project partnerships, a map of the location where there will be water system upgrades, a subdivision plan, and emergency & other key contact information. An Information Kiosk is located at the corner of Lytton-Lillooet Highway (Highway 12), and Alkali Road. The Kiosk includes information about: the Nuuautin IR 2B Subdivision and Water System Improvement Projects, the project partnerships, a map of the location where there will be water system upgrades, a subdivision plan, and emergency & other key contact information. NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS WWW.APLINMARTIN.COM/LFNSUBDIVISION WWW.APLINMARTIN.COM/LFNWATERSYSTEM NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS WWW.APLINMARTIN.COM/LFNSUBDIVISION WWW.APLINMARTIN.COM/LFNWATERSYSTEM NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS WWW.APLINMARTIN.COM/LFNSUBDIVISION WWW.APLINMARTIN.COM/LFNWATERSYSTEM NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS WWW.APLINMARTIN.COM/LFNSUBDIVISION WWW.APLINMARTIN.COM/LFNWATERSYSTEM If you have any additional question please contact us. We will reply to all enquiries, comments, and questions. If your feedback requires a response from Council, it will be forwarded to Council by an administrator. If you have any additional question please contact us. We will reply to all enquiries, comments, and questions. If your feedback requires a response from Council, it will be forwarded to Council by an administrator. At LFN Town Hall meetings If you have any additional question please contact us. We will reply to all enquiries, comments, and questions. If your feedback requires a response from Council, it will be forwarded to Council by an administrator. At LFN Town Hall meetings At LFN Town Hall meetings

M IMPROVEMENT PROJECTS

NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS WWW.APLINMARTIN.COM/LFNSUBDIVISION WWW.APLINMARTIN.COM/LFNWATERSYSTEM

Page 1 Page 2 Page 3 Page 4 Page 5 Page 6

Made with FlippingBook - Online catalogs