Not Completed
Completed
Status Indicator
Goal 5: Action Items Continued
Responsible Party
Status Explanation
5.6 Ensure all future facility designs sustain operations for more than 25 years. New facilities must function efficiently, be located in optimal areas, and have the opportunity for future expansion in order to effectively serve the community, encourage police and community interaction, and limit the need for new capital dollars.
Research & Planning, Finance/Personnel Bureau
Each year Research & Planning reviewed plans for new facilities and ensures that each will be programmed to accommodate future growth and service needs.
Research & Planning, Finance/Personnel Bureau
Research & Planning continued to evaluate opportunities as they arise. Police and Fire are partnered on a Property Room Expansion and Arson/Bomb Squad Evidence Room.
5.7 Seek co - location opportunities with other departments and entities, as appropriate.
5.8 Evaluate the use/effectiveness of all storefronts, and recommend whether their use should continue in the future, discontinue, or relocate to different locations.
Research & Planning, Finance/Personnel Bureau
Research & Planning continued to evaluate all storefront leases.
5.9 Utilize leased facilities only when necessary for operational effectiveness, and where possible, reduce the number of leased facilities by FY21.
Research & Planning, Finance/Personnel Bureau
Research & Planning evaluated all leases. Leases were reduced by 6 facilities.
Research & Planning, Finance/Personnel Bureau Communications & Technology Services, Finance/Personnel Bureau
5.10 Ensure that future police facilities are designed to maintain critical operations in the event of a disaster.
All future police facilities are reviewed and programmed to accommodate future growth and service needs.
5.11 Review security of existing Police Department facilities and make improvements as necessary to implement best practices and comply with Criminal Justice Information Systems (CJIS) standards.
Technology needs were reviewed as needed.
Back to the Table of Contents
4. Technology Development & Infrastructure Expansion
35
Strategic Plan - Final Implementation Progress Report