There is no progress without building. And building we are! The construction of the Main Plant equipment stor- age area is moving right along despite the settling in of the cold weather. Soon the building will be enclosed so the construction workers can work indoors. On Main Street our new Consumer Lab is just about ready to be occupied. We have some people who are very eager to move into their new lab facility. Out west things are just getting a good start. Ground has been broken and footings poured. Every week we see progress and change. Construction Update

Ingredient Division Warehouse - Doesn’t look like a lot, but footings are in and all the site work is complete. The building will start going up towards the end of December and Mother Nature will determine how fast we move.

New Mixer for Contract Packaging - This project has taken longer than what we thought it would, but setting up a new mix system is not as easy as just plugging it in. We are in the process of fine tuning the electronics and getting the metal detection system designed. We hope to see this fully opera- tional by the middle of January.

Consumer Products Lab - We are getting really close on this one. This facility should be ready for occupancy by early January. Betty Crocker herself will be jealous of these kitchens - look for a full story in the next Crest Ink.

16 Crest Ink January, February & March 2015

Made with FlippingBook - Online Brochure Maker