AUTHORITY PROJECT SUMMARY HT-3020 BALTIMORE HARBOR TUNNEL (BHT) LANE USE SIGNAL (LUS) EXTENSION

PIN NUMBER CONTRACT NUMBER CONTRACT TITLE

MDTAPRJ002587 HT-3020-0000 BALTIMORE HARBOR TUNNEL (BHT) LANE USE SIGNAL (LUS) EXTENSION

PROJECT SUMMARY

The work to be performed under this contract is located at the I-895 Baltimore Harbor Tunnel (BHT) facility between the north portal of BHT and north of Lombard Street Interchange in Baltimore City. The project will extend the existing Lane Use Signal (LUS) system through the corridor to improve the two-way traffic operations in the tunnel.

SCHEDULE

ADVERTISEMENT DATE

($)

1/7/2025

ANTICIPATED NOTICE TO PROCEED DATE

Advertised GOAL (%)

Proposed GOAL (%)

Jul-25

DURATION (CALENDER DAYS)

MBE PARTICIPATION

730

OVERALL MBE

19.00% 0.00% 0.00% 0.00% 0.00% 1.00%

23.21% 0.00% 0.00% 0.00% 17.19% 1.00%

AFRICAN AMERICAN ASIAN AMERICAN HISPANIC AMERICAN

WOMEN

VSBE

ENGINEER'S ESTIMATE (EE)

$8,088,817.44

BID RESULTS

BID AMOUNT ($)

% VARIANCE TO EE

NO ☒

BID PROTEST

YES

McLean Contracting Company Mona Electric Group, Inc

8,557,000.00 10,747,639.70 11,122,567.80

5%

32% 37%

FUNDING SOURCE

100% TOLL REVENUE

Aldridge Electric, Inc