KB-4903-0000 - Key Bridge Rebuild Progressive Design-Build Early Work Package Funding Approval Page 2
critical path, including continued pile installation, trestle installation, footing material procurement, additional pile material procurement, and long lead construction items. This work requires the authorization of an additional $150,000,000.00 in early works funding, increasing the not-to-exceed authorization to $495,000,000.00. The cumulative total of all EWPs shall not exceed $495,000,000.00 without MDTA Board approval. RECOMMENDATION To provide approval of an additional $150,000,000.00 in Early Works Package funding for contract KB-4903-0000, with a revised not-to-exceed amount of $495,000,000.00.