LOFTLINES BELFAST PROJECT PROFILE

Building Services team throughout this project, and I am immensely proud of our own team, along with our supply chain and subcontractor partners, whose commitment, collaboration and expertise were instrumental in delivering a successful outcome.”

worked on the project at peak times. Led by managers for operations, electrical and mechanical contracting, the team included separate electrical, mechanical and QA supervisors for each block as well as labour, logistics and admin staff. AEM also managed multiple sub-contractors, working across individual or sometimes all three blocks. Martin Devlin, AEM Operations Manager and Project Manager for Loftlines, says, “PC

panel heaters to TV, IRS, data and fibre broadband. “We delivered the full MEP scheme from every apartment to the amenity areas,” says Martin. “While there was a phased handover of the blocks with the social and affordable housing block the first to be completed, the biggest challenge was all three projects were underway at the same time, so each had to be structured independently to avoid any delays to the tight schedule.

Established in Belfast, AEM is one of Ireland’s leading electrical and

mechanical building services and facilities management contractors. With offices in Belfast, London and Scotland, the company is well positioned to deliver projects and services across the UK and Ireland. A supporter of the Lighthouse Charity, AEM hosted a Make It Visible team talk from the construction industry charity focused on the importance of positive mental health and wellbeing on site at Loftlines in September 2025.

was granted in July 2026, and tenants have already moved into each block. There was quite a lot to do from initial planning to first fix to handover and commissioning; it’s been a busy two years for the AEM Loftlines team.” AEM’s electrical package included central switch and distribution boards,

“Everyone played their part, and we have delivered a great project which is going to be part of the Belfast skyline for years to come.”

“The apartment installation concept was to coordinate a train of all trades within a 14-week apartment programme from first fix to final fix, with each sub- contractor allocated one to two weeks to complete their particular section to release the following trades. QA was a major

apartment consumer units, containment, generators and ATSs and wiring accessories. Alongside lighting, lighting controls, lighting protection and an aircraft warning lighting system, security and alarm solutions included access control, CCTV and door entry intercom, disabled refuge and fire alarms. Further services range from electric

focus, to ensure walls and ceilings could be closed around the follow-on trades. All QA was record digitally. “AEM has worked successfully with GRAHAM for many years and looks forward to continuing this strong partnership into the future. We developed an excellent working relationship with the GRAHAM

208 City Business Park, Dunmurry, Belfast BT17 9HY T: +44 (0)28 9062 8574 E: info@aem-ltd.com www.aem-ltd.com Want to know more?

www.elecmagazine.com FOLLOW US ON:

IRELAND’S ELECTRICAL MAGAZINE | 21

Made with FlippingBook - professional solution for displaying marketing and sales documents online