TENTATIVE PROJECT TIMELINE
PROJECT TIMELINE - WESTPORT
PROJECT START:
PROJECT END:
91 working days
MONTH 2
MONTH 4
MONTH 6
MONTH 1
MONTH 3
MONTH 5
WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12 WEEK 13 WEEK 14 WEEK 15 WEEK 16 WEEK 17 WEEK 18 WEEK 19 WEEK 20
1st PAYMENT RECEIVED
4th PAYMENT LAST PAYMENT 2nd PAYMENT 3rd PAYMENT
Materials Procured Materials Received
COMPRESSED AIR BUOYANC Y CAB fabrication
CAB on-site
CAB installation
CAB testing
CAB commissioning
VERTICAL AXIS WIND TURBINE Storage tank ordered
Storage tank ready Storage tank on-site Storage tank installation Storage tank testing
FLOWER STRUCTURE AND SOLAR TRACKER Structure ordered
Structure ready Structure on-site Structure installation Structure testing