A complete list of planned capital projects for 2027 follows: ■ 2027 CAPITAL PROJECTS OVERVIEW
PROJECT TYPE
ESTIMATED COST
A Capital Projects B Capital Projects
$2,700,000 $8,200,000 $650,000 $1,400,000 $515,000 $955,000 $3,200,000 $820,000 $18,440,000
Annual Building Capital Projects (ABC) Asset Maintenance Projects (AM) Information Technology Projects
Vehicles and Equipment Golf Capital Projects
Districtwide Capital Improvements and Projects (see chart below for further detail)
TOTAL
A CAPITAL PROJECTS - $2,700,000
A CAPITAL PROJECTS
PARK NAME
PROJECT
ESTIMATED COST
Country Commons Creekside Park Cress Creek Park Plank Road Park Springhill Park
Renovate playground Renovate playground Renovate playground
$300,000 $350,000 $300,000 $540,000 $280,000 $930,000 $2,700,000
Develop new park and playground
Renovate playground
Wolf’s Crossing Community Park
New ballfields (2)
TOTAL
2027 BUDGET 88
napervilleparks.org
Made with FlippingBook - Online magazine maker