Hillsborough County Greenways and Trails Master Plan

Planning - Level Cost Estimates

The estimates in Figure 15 are for ten of the Greenway Corridors identified in the plan. These corridors repre- sent a range of project types and magnitudes.

These estimates are for planning purposes and, therefore, are informational. Estimates will be refined to re- flect other surface materials and desired amenities as specific projects progress through the project develop- ment and environment and design phases.

Figure 15. Selected Vision Greenways cost estimates

Cost Range Esti- mate (2023 dol- lars)

Surface Type

Length (approx. miles)

Selected Vision Greenway

Memorial Bikeway: Upper Tampa Bay Trail to Memorial Road

Paved

2.3

$3.22M— $5.06 M

Memorial Bikeway: Upper Tampa Bay Park to George Road

Paved

6.9

$9.66M— 15.18 M

Northwest Plant City Greenway

Paved

13.4

$18.76M— $29.48 M

South Hillsborough Pipeline Trail: Lumsden Rd to Lithia Pinecrest Rd, and Fishhawk Sports Complex to Hometown Ln along Fishhawk

Paved

6.4

$8.90M— 13.99 M

Shell Point Road: Cedar Drive - 15th Street SE

Paved

3.3

$4.62M— $7.26 M

South Coast Greenway, Phase V: Progress Vil- lage (66th Street S to US Highway 41 S )

Paved

4.4

$6.16M— 9.68 M

South Coast Greenway, Phase VII: Palm River (Selmon Expressway – Madison Avenue)

Paved

3.6

$5.04M— $7.92 M

Grand Alafia Hiking Loop

Unpaved

30.3

$8.7M— 11.8 M

Hillsborough Preserve Connector

Unpaved

31.3

$9M— $12.2 M

Typical Blueway

Blueway

NA

$1,000 — $1 M

1. The segment of the South Hillsborough Pipeline Trail along Lithia Pinecrest Road is not included. It is being studied separatelyand will be included in the Lithia Pinecrest Shared Use Path, part of an ongoing Project Development and Environment (PD&E) Study.