PARTNERING WITH CHARLOTTE COUNTY UTILITIES O’Hara Blvd & Fallon Cir

Charlotte County Sheriff’s Office reached out to Public Works to advise that a water line break had occurred causing the roadway to cave in. An emergency traffic advisory was sent out and the road was closed for repairs. The Charlotte County Utilities (CCU) Department located the line break and started conducting a repair, while the Public Works Maintenance & Operations (M&O) team removed unsuitable material and began backfilling the area. Once backfill was completed the contractor restored the asphalt measuring 43ft x 26ft, with Fallon Circle being 2in thick and O'Hara Boulevard being 6in thick.

Midway Blvd X Achilles St

The M&O team performed asphalt restoration following a water main break at the intersection of Midway Boulevard and Achilles Street when a contractor accidentally damaged the 16in water main, CCU quickly sprang into action to repair the break and restore service. M&O open cut the westbound lanes (from sidewalk to median) to reveal the erosion underneath the lanes. The diameter of the erosion (closest to the westbound sidewalk) was approximately 12.5in and gradually became smaller as they approached the median. M&O successfully completed asphalt restoration as shown in the photo above.

6 0

**FT = Feet **IN = Inch/es

Made with FlippingBook Annual report maker