ACTION PLAN
Estimated Timeframe Estimated Duration
Estimated Costs
Immediate: Within 2 years
Less than 1 year
Up to $250,000
Short: 2-5 years
1-2 years
$250,000 - $500,000 $500,000 - $1 million More than $1 million
Medium: 5-10 years
More than 2 years
Long: More than 10 years
*Indicates costing is includes in the estimates on pages 196-197
1. Enhance East-West connectivity throughout the corridor to distribute trips across a greater network Action # Description Related Goals Timeframe Duration Cost
Update the City’s Master Thoroughfare Plan to include identified connections for Westshore Way, Fitzhugh Avenue/Crenshaw Avenue, Eastland Street/Greyson Street, and Hardeman Street/Garden Lane
Travel Options, Connectivity
$
1.1
Immediate
Connect Fitzhugh Avenue / Crenshaw Avenue from US-287 to Loop 820
Travel Options, Connectivity
$$$
1.2
Long
Travel Options, Connectivity
$$$
1.3
Connect Eastland Street / Grayson Street from US-287 to Loop 820
Long
Connect Hardeman Street / Garden Lane from US-287 to Carey Street
Travel Options, Connectivity
$$$
1.4
Long
Design and construct roadway connection between Donalee Street and Freddie Street
Travel Options, Connectivity
$$
1.5
Medium
Implementation | 199