10. Integrate smart corridor technology and continue to upgrade utilities

Action #

Description

Related Goals Timeframe Duration

Cost

Upward Mobility, Connectivity

$$

10.1

Install fiber optics along East Berry Street.

Medium

Community Building, Connectivity

$$$$

10.2

Install cooling pavement along East Berry Street.

Long

Explore opportunities to expand free public Wi-Fi throughout the corridor. Utilize water main modeling to adequately size and align future density with future needs.

Upward Mobility, Connectivity

$

10.3

Medium

Community Building, Connectivity Community Building, Connectivity Community Building, Connectivity Community Building, Connectivity Community Building, Connectivity Community Building, Connectivity Community Building, Connectivity

$

10.4

Short

Replace degraded or age-appropriate water main lines in conjunction with reconstruction on East Berry Street.

$$$$

10.5

Medium

Replace linear footage of 6-inch water mains to meet minimum standard on East Berry Street.

$$$$

10.6

Medium

Relocate existing water meter locations and replace undersized meters as needed.

$$$$

10.7

Medium

Replace oversized water mains to service property owners as reconstruction occurs along East Berry Street.

$$$$

10.8

Medium

Utilize sanitary sewer modeling to adequately size and align future density with sanitary sewer mains along East Berry Street.

$

10.9

Short

VCP sanitary sewer line replacement from manhole to manhole should be considered during reconstruction of East Berry Street

$

10.10

Medium