INTEGRATION NEWS Carter Day dryer production integration into MAAG Roanoke/Granby facility is getting one more step closer to completion. Below are the most recent updates: Facility: • Installation of the 26' tall bay door completed. • Installation of the 20' tall bay door at the loading dock completed. • Dock lock and leveler to be installed in August. • Electrical rough in for the new switchgear has begun. • All the plastic covering the insulation on the walls has been cleaned. • Jib cranes have been removed. • Plating over the rails in the floor has begun. • We had to cut/dig a hole at one of the building columns in order to determine the size of the existing footers in order to finalize design/layout of the assembly and rotor cranes. Engineering: • Continues to implement the CD designs into our system. The D50 series and major AUDU's will be implemented within 2025.