BALLFIELD AND OUTDOOR COURT RESTORATION UPDATE
BALLFIELD UPDATE
Even though contractors have faced many weather delays, the new Musco lighting system has been installed; grading & irrigation work has been completed; fencing, sod and shade structure work will continue in March and April. The projected reopening date is early May 2024!
OUTDOOR COURT UPDATE:
The new light poles and fixtures, fencing and asphalt foundation has been completed! Contractors are waiting on temperatures to hold consistently above 65 degrees to progress to the next phase of surfacing work and net installation. Projected reopening in early April 2024!
12