PLEASE SEE THE WEEKLY SNAPSHOT OF CURRENT ACTIVITY AT THE CLUBHOUSE.
BUDGET
• Previously issued
DESIGN CONSULTANTS
P+L • FFE installations on the 2nd Floor started this week and will continue through next week.
• FFE installations on the 1st Floor were completed 2 weeks ago • FFE installations for outdoor furniture are scheduled for Nov. 12th.
Insite Studio • Monitoring the landscape installation to verify that the PBG Forrester will approve final inspections once complete.
Civil Design Inc • Punch list was completed in September, and repairs are in progress by Proctor.
PROCTOR CONSTRUCTION
Schedule • Hood Grease duct work to repair ducts is in progress in all kitchens. They have been repairing welds that were not liquid tight. It is a time consuming process to grind the welds, reweld and test for any leaks. Proctor previously provided an estimated schedule of completion that runs through mid-November. They will be updating the schedule at the end of this week. • Proctor will provide weekly updates on progress • Exterior Paint final touch ups are in progress and will continue for a few weeks. • ADA bathroom revisions in progress Inspections • Final fire inspections are in progress. BDA system appears to be one of the last items related to occupancy. They need to add two additional antennas. They are anticipating this being complete by the end of October