CraneHoist 20230703v1

Operations training

Crane and Hoist / V1 2023-07-03

 GOOD PRACTICE: Remember the job is not finished until the clear-up is done! Always clear away the lifting tackle, lifting gear, load bearers and dunnage after use.  PRECAUTIONS: If you are unsure of the correct lifting or slinging method then consult your lift controller (CP). The lift controller shall act as overall supervisor for this basic auxiliary lift and monitoring the associated risk assessment (TRA 01) for compliance. Do not attempt the lift if you are uncertain of your ability to complete it safely without risk to yourself and others.

BASIC LIFTING PLAN

Location :

Area :

Wind Jackup - Wind Farm 1

Starboard side

Permit No.:

Risk Assessment :

WJ-001

TRA 01

Lifting Plan No .:

WIND JACKUP 001

Task Details (Step By Step) Yes

Below

Is Diagram/Sketch of Lifting Operation Enclosed? Yes

Description Of Lifting Operation : Lift one generator off CTV to deck of Wind Jackup at Wind Farm 1. Lifting Equipment to be used for lift : X1 4.75T Shackle X1 WLL 5T - EWL 5M Round Sling

Weight of Load :

<900Kg

ACTUAL – Generator Atlas Copco QAS 20

Crane: LIEBHERR LTM 1100 Duty : 900Kg @ 24m Load(s) : generator only, Max 900 kg Lifting Equipment : approx. 5 kg Total Load : 905 kg % Capacity used : 80% Competency 1) CTV Crew must/will have the required slinger banksman competence 2) All crew involved with handling the load must/will have slinger banksman competence for releasing generator on deck/final position

Task Details (Step-by-Step)