INTEGRATION NEWS

House cleaning continues at the Granby facility and installation of the new LED lighting is complete.

The owner of the building has conducted demolition of the wash bay wall and removed piping and electrical from the area that will be used for balancing the rotors. The columns for the rotor assembly crane have been laid out. Meetings have been conducted with third party engineers for design of the footers for the cranes as well as with the contractor that will install the footers.

MAAG IT/Maintenance are installing new conduit runs to relocate the main core switch rack and wireless access points.

Everyone’s support and efforts are truly appreciated. If you have any questions, please feel free to contact me. George Benoit Integration Manager