Consolidated Transportation Program CTP FY 2025-2030

MARYLAND TRANSPORTATION AUTHORITY -- Line 8

Primary Construction Program

PROJECT: I-95 Fort McHenry Tunnel - Rehabilitate Substructure and Superstructure of Various Bridges on I-95 in Baltimore City DESCRIPTION: Repair substructure and superstructure of seventy-four bridges on I-95 in Baltimore City. The work includes structural weld repairs, structural steel repairs, roadway joint repairs, concrete repairs, and application of protective coatings on seventy-four bridges. Originally only Phase 1 was funded. Funding for Phase 2 is now added. Each phase includes thirty-seven bridges.

PURPOSE & NEED SUMMARY STATEMENT: The annual facility inspections, as well as findings and issues noted by MDTA Operations, have identified the need to perform a comprehensive substructure and superstructure rehabilitation throughout this facility.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: X Enhance Safety and Security

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

X

Promote Environmental Stewardship

Deliver System Quality

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: The bridges show signs of deterioration. Rehabilitation will improve condition of the bridges' substructure and superstructure.

PFA Status Yet to Be Determined

Exception Granted

STATUS: Engineering is complete. Construction is underway.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

PHASE

ESTIMATED EXPENDED PREVIOUS

CURRENT

BUDGET

PLANNING

SIX

BALANCE SIGNIFICANT CHANGE FROM FY 2024 - 29 CTP: Cost increased by $5.0 million due to additional MDTA Police, Maintenance, and Phase V Construction services. TO

COST

THRU YEAR

YEAR

YEAR

FOR PLANNING PURPOSES ONLY

YEAR

($000) CLOSE YEAR 2024

2025

2026

...2027... ...2028...

...2029...

...2030...

TOTAL

COMPLETE

Planning

0

0

0

0

0

0

0

0

0

0

0

Engineering

4,885

4,885

0

0

0

0

0

0

0

0

0

Right-of-way

0

0

0

0

0

0

0

0

0

0

0

Utility

0

0

0

0

0

0

0

0

0

0

0

Construction

27,441

24,783

10,793

2,657

0

0

0

0

0

2,657

0

Total

32,326

29,668

10,793

2,657

0

0

0

0

0

2,657

0

Federal-Aid

0

0

0

0

0

0

0

0

0

0

0

TOLL

32,326

29,668

10,793

2,657

0

0

0

0

0

2,657

0

Other

0

0

0

0

0

0

0

0

0

0

0

2397, 2513

PAGE

MDTA--8