Consolidated Transportation Program CTP FY 2025-2030

MARYLAND TRANSPORTATION AUTHORITY -- Line 28

Primary Development & Evaluation Program

PROJECT: US 50/301 Bay Bridge - Tier 2 NEPA Study

DESCRIPTION: The Bay Crossing Study Tier 2 NEPA is the second stage of the two-tiered federally required National Environmental Policy Act (NEPA) process. The Bay Crossing Study Tier 1 NEPA was approved by FHWA in April 2022, identifying Corridor 7, the corridor containing the existing Bay Bridge, as the Selected Corridor Alternative. Tier 2 studies specific alignment, crossing type and potential number of lanes needed within the 2-mile wide, 22-mile long corridor from Severn River Bridge to the US 50/301 split. Tier 2 involves significant public engagement and participation. Project delivery method options will be determined.

PURPOSE & NEED SUMMARY STATEMENT: The Bay Crossing Study Tier 2 NEPA is the next step in the strategy to address congestion and future traffic demand crossing the Chesapeake Bay. It must be completed before final design and construction could potentially begin if a build alignment alternative is selected.

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

PFA Status Yet to Be Determined

Exception Granted

STATUS: Planning is underway.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

PHASE

ESTIMATED EXPENDED PREVIOUS

CURRENT

BUDGET

PLANNING

SIX

BALANCE SIGNIFICANT CHANGE FROM FY 2024 - 29 CTP: Decreased by $2.1 million for less than anticipated costs.

COST

THRU YEAR

YEAR

YEAR

FOR PLANNING PURPOSES ONLY

YEAR

TO

($000) CLOSE YEAR 2024

2025

2026

...2027... ...2028...

...2029...

...2030...

TOTAL

COMPLETE

Planning

25,924

11,937

7,263

6,987

7,000

0

0

0

0

13,987

0

Engineering

0

0

0

0

0

0

0

0

0

0

0

Right-of-way

0

0

0

0

0

0

0

0

0

0

0

Utility

0

0

0

0

0

0

0

0

0

0

0

Construction

0

0

0

0

0

0

0

0

0

0

0

Total

25,924

11,937

7,263

6,987

7,000

0

0

0

0

13,987

0

Federal-Aid

0

0

0

0

0

0

0

0

0

0

0

TOLL

25,924

11,937

7,263

6,987

7,000

0

0

0

0

13,987

0

Other

0

0

0

0

0

0

0

0

0

0

0

2586

PAGE

MDTA--28

Made with FlippingBook - Share PDF online