Consolidated Transportation Program CTP FY 2025-2030

MARYLAND TRANSPORTATION AUTHORITY -- Line 3

Primary Construction Program

PROJECT: I-95 John F. Kennedy Memorial Highway - I-95 Southbound Hard Shoulder Running

DESCRIPTION: This project will provide part-time left shoulder use for approximately 5.4 miles on I-95 southbound from Maryland House to MD 24 in Harford County. It involves restriping I-95 and repaving the left shoulder lane to accommodate part-time left shoulder use. Installation of Intelligent Transportation System (ITS) devices to dynamically open and close the left shoulder lane based on traffic conditions is included.

PURPOSE & NEED SUMMARY STATEMENT: This project will increase capacity along southbound I-95 between Maryland House and MD 24 and reduce congestion during high traffic volumes. The part time shoulder will be utilized during prescheduled peak periods and during unforeseen spikes in demand.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: Enhance Safety and Security X

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

X

Promote Environmental Stewardship

Deliver System Quality

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: This segment of I-95 currently operates at an unacceptable level of service with significant delays on summer weekends and the Maryland House On-Ramp is a high frequency crash location with approximately 75% of crashes occurring on the weekends. This project will increase capacity and improve safety, particularly during summer weekends, to alleviate severe congestion, delays and crashes along southbound I-95 between the Maryland House and MD 24.

PFA Status Yet to Be Determined

Exception Granted

STATUS: Engineering is underway. Construction will begin in FY 2026.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

PHASE

ESTIMATED EXPENDED PREVIOUS

CURRENT

BUDGET

PLANNING

SIX

BALANCE SIGNIFICANT CHANGE FROM FY 2024 - 29 CTP: Cost increased by $3.1 million due to unit cost inflation from

COST

THRU YEAR

YEAR

YEAR

FOR PLANNING PURPOSES ONLY

YEAR

TO

project delay. Project was originally anticipated to Advertise in early FY 23 but is now anticipated to be Advertised in early FY 26 due to delays outside of the projects control.

($000) CLOSE YEAR 2024

2025

2026

...2027... ...2028...

...2029...

...2030...

TOTAL

COMPLETE

Planning

0

0

0

0

0

0

0

0

0

0

0

Engineering

3,060

2,793

809

267

0

0

0

0

0

267

0

Right-of-way

0

0

0

0

0

0

0

0

0

0

0

Utility

0

0

0

0

0

0

0

0

0

0

0

Construction

35,400

0

0

0

6,029

15,726 10,594

3,051

0

35,400

0

Total

38,460

2,793

809

267

6,029

15,726 10,594

3,051

0

35,667

0

Federal-Aid

0

0

0

0

0

0

0

0

0

0

0

TOLL

38,460

2,793

809

267

6,029

15,726 10,594

3,051

0

35,667

0

Other

0

0

0

0

0

0

0

0

0

0

0

202

PAGE

MDTA--3