Consolidated Transportation Program CTP FY 2025-2030

MARYLAND TRANSPORTATION AUTHORITY -- Line 5

Primary Construction Program

PROJECT: I-95 John F. Kennedy Memorial Highway - I-695 Ramps to I-95 Northbound Express Toll Lanes DESCRIPTION: Construct two I-95 Section 100 ETL Ramps from I-695 Eastbound and Westbound to I- 95 Northbound ETLs.

PURPOSE & NEED SUMMARY STATEMENT: The two ETL ramps are a part of the connectivity between two major interstate roadways and specifically the northbound ETLs. This allows traffic on I-695 a choice to use the NB General Purpose (GP) lanes or the NB ETLs. This improvement will reduce the volume of traffic traveling onto the GP lanes and thereby improves traffic operation on the I-95 facility.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: X Enhance Safety and Security X

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

X

Promote Environmental Stewardship

Deliver System Quality

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: Once open, these I-695 ramps will provide access to I-95 NB ETLs for a distance of approximately 12 miles.

PFA Status Yet to Be Determined

Exception Granted

STATUS: Engineering is underway. Construction to begin in FY 2026.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

PHASE

ESTIMATED EXPENDED PREVIOUS

CURRENT

BUDGET

PLANNING

SIX

BALANCE SIGNIFICANT CHANGE FROM FY 2024 - 29 CTP: Added to the Construction Program.

COST

THRU YEAR

YEAR

YEAR

FOR PLANNING PURPOSES ONLY

YEAR

TO

($000) CLOSE YEAR 2024

2025

2026

...2027... ...2028...

...2029...

...2030...

TOTAL

COMPLETE

Planning

0

0

0

0

0

0

0

0

0

0

0

Engineering

5,425

3,170

1,359

2,055

200

0

0

0

0

2,255

0

Right-of-way

0

0

0

0

0

0

0

0

0

0

0

Utility

100

0

0

0

100

0

0

0

0

100

0

Construction

73,600

0

0

0

20,750

37,700 14,850

300

0

73,600

0

Total

79,125

3,170

1,359

2,055

21,050

37,700 14,850

300

0

75,955

0

Federal-Aid

0

0

0

0

0

0

0

0

0

0

0

TOLL

79,125

3,170

1,359

2,055

21,050

37,700 14,850

300

0

75,955

0

Other

0

0

0

0

0

0

0

0

0

0

0

2582

PAGE