20250324 HV V0 DRAFT

Operations training

High Voltage Standard / V0 - DRAFT 2025-03-21

Ask open-ended questions of participants on safe lifting for cable pulling operations:

The participants shall:

Contribute to reflective discussion on safe lifting for cable pulling operations

Practice the application of correct planning and control for the lifting operation, including pre- inspection

COMPLETING THE CABLE PULL

30 min.

The aim of this lesson is to prepare participants to ensure HV cable pulling operations are completed thoroughly, safely and effectively with quality, ensuring that cable is installed securely in place.

After having successfully completed this lesson, the participants can:

55) Act independently to complete the cable pulling process, ensuring secure placement, fastening, protection of cable and site restoration (Ability, intermediate level)

ELEMENT 9.1 - CABLE FASTENING

To achieve the lesson learning objectives, the participants can:

56) Distinguish how to securely fasten HV cables using cleats (Skills, intermediate level)

57) Explain methods for securing cables to prevent mechanical or environmental damage (Knowledge, intermediate level)

The instructor shall:

Demonstrate tools, equipment and techniques for HV cable fastening including:

a. Use of cable cleats of different types, showing correct use of each

b. securely fastening HV cable in place without damage

c. how to determine when the cable is sufficiently secured

Global Wind Organisation / www.globalwindsafety.org

96 / 114

Made with FlippingBook flipbook maker