INDIGENOUS SERVICES CANADA (ISC) FUNDING PROGRAM
FAR (Feasibility Application Request): This application is made during the initial planning stage. This funding enables feasibility studies to be conducted to assess the project’s viability. Indigenous communities and/or organizations who are seeking funding for capital projects through ISC must adhere to structured funding programs. The FAR, DAR, and PAR are applications paired with cost estimate reports to request funding at different stages of a project.
DAR (Design Application Request): This application is made to initiate the design phase once the project is deemed feasible. This funding enables spending of funds necessary to complete the project design.
PAR (Project Application Request): This application is made to enable the construction phase. This funding enables the construction of the project, permitting the spending of the remaining project funds.
September
March
March / April
PROJECT TIMELINE
PAR FUNDING SUBMISSION (Subdivision)
PRELIMINARY PAR FUNDING RESUBMISSION (for the Subdivision) Preliminary resubmission, SARA permit required prior to full approval.
PRELIMINARY PAR FUNDING SUBMISSION (for the Water System Improvement) Preliminary submission, SARA permit required prior to full approval.
2022-2023
FAR FUNDING SUBMISSION AND APPROVAL
July
DAR FUNDING APPROVAL
FUNDING
02
04
06
08
10
12
02
04
06
DELIVERABLES
DESIGN PHASE
May
August
January
Subdivision and Water System Improvement Pre-Design
Subdivision and Water System Improvement Design
Submission of SARA Permit Applications
CONSTRUCTION PHASE
CONSTRUCTION
June
Fall 2026
Site Activation/ Construction
Construction Completion Target
NUUAUTIN IR 2B SUBDIVISION AND STEIN WATER SYSTEM IMPROVEMENT PROJECTS WWW.APLINMARTIN.COM/LFNSUBDIVISION WWW.APLINMARTIN.COM/LFNWATERSYSTEM