INTEGRATION NEWS
Facility: - GPS surveying was conducted at the Granby facility to confirm structural steel elevations to ensure no interference with the 20- ton crane design - Installation of the dock leveler and dock lock has been completed Manufacturing/Assembly: - Components for the D1050 dryer are currently being peened - Welding for the first AUDU4000 has begun - Received the top lifting device for D50 series dryers. Also received carts for moving the solid rotor
AUDU4000 in Welding
Carts and Top Lifting Device
(Continues on the next page)