8.4
Damage to Facilities 8.4.1 SaskEnergy is responsible for damages to SaskEnergy Facilities that are caused by ordinary wear and tear or by the negligence of SaskEnergy, its Subsidiaries or any of their officers, directors, employees or agents. 8.4.2 Customers are responsible for maintenance, Service, and repairs downstream of the Metering Point, which is generally the outlet side of the meter. Amended – October 16, 2014 Encroachments on Facilities or Right-of-Way 8.5.1.1 No Person shall construct or allow the construction of any building or other structure over any of the regulators, shut-off valves, meters, pipelines, Service Lines, Main Lines or other Facilities of SaskEnergy or a Subsidiary of SaskEnergy without the prior consent of SaskEnergy or its Subsidiary. Amended – May 15, 2017
8.5
8.5.1.2 In accordance with Section 7.1 of the Regulations, no Person shall: (a)
undertake a Site Disturbance within a SaskEnergy Facility right of way without the consent of SaskEnergy; where no right of way exists, undertake a Site Disturbance over or with 1.5 metres of the SaskEnergy Facility without the consent of SaskEnergy. Amended – May 15, 2017
(b)
8.5.1.3 Where consent of SaskEnergy is required to undertake a Site Disturbance, or consent of SaskEnergy is otherwise required for an activity or installation, consent is deemed granted in the circumstances described in Appendix F, provided the terms and conditions thereof are met. Consent of SaskEnergy shall otherwise be counterparty specific, and in writing. New Provision – May 15, 2017 8.5.2 If, in the opinion of SaskEnergy or its Subsidiary, a building or structure over or near any of the regulators, shut-off valves, meters, pipelines, Service Lines, Main Lines or other Facilities of SaskEnergy or its Subsidiary constitutes a safety hazard, SaskEnergy or its Subsidiary may demand in writing that the Owner of land on which the building or structure is situated remove the building or structure at the Owner’s expense. Amended – February 8, 2008 8.5.3 If an Owner fails to comply with a written demand pursuant to [8.5.2] within the time specified in the demand, or any further time that SaskEnergy or its Subsidiary may allow, SaskEnergy or its Subsidiary may enter on the land and do any of the following that it considers necessary to remove a safety hazard:
(a) (b) (c) (d)
Remove the building or structure; Re-route a pipeline, Service Line, or Main; Install a new pipeline, Service Line, or Main;
Move any regulator, shut-off valve, meter or other Facility of SaskEnergy or its Subsidiary. Amended – February 8, 2008
8.5.4 SaskEnergy or its Subsidiary may charge the Owner with SaskEnergy’s or its Subsidiary’s costs in carrying out any of the activities mentioned in subsection [8.5.3]. Amended – February 8, 2008