Project Sheet - Flare Tip Replacement

FLARE TIP PROJECTS

Project Offshore flare tip replacement

Project Design of temporary lifting davit to replace a flare tip offshore Client Shell FPSO

Project Offshore flare tip replacement

Client AMNI International Petroleum Development Location Nigeria

Client Noble Energy

Location North Sea

Location Equatorial Guinea

Zenith Structural Access Solutions Limited was awarded a contract by AMNI International Petroleum Development Company Limited to design and install a temporary lifting frame. This frame facilitated the replacement of a 907kgs flare tip located on a FPSO offshore in Nigeria. We completed the design, supply, and installation of the temporary lifting frame in-house. Our safe method results in significant cost savings when compared with expensive helicopters and barge cranes.

Shell appointed Zenith to design and install a temporary lifting davit, to facilitate the replacement of a 710 kg flare tip on Shell’s FPSO Curlew located in the North Sea.

The outage work scope included the removal and replacement of the existing flare tip, the flare tip is located on an elevated boom structure. Zenith designed and fabricated a bespoke temporary lifting frame for installation to the existing upper flare derrick to allow the removal of the existing flare tip and the installation of the replacement flare tip (2267 kg).