Safety training
GWO Solar Safety Training / V1 02072025
9.4 Equipment for the Safe Solar Work Module The equipment required for manual handling must be representative to loads commonly handled at utility scale Solar PV sites as well as representative to work situations in the solar industry. Training equipment must comply with national requirements as stated in GWO Requirements for Training.
The equipment required for training as listed in Annex 1 must be available and must comply with any national regulatory requirements, where applicable.
9.5 Safe Solar Work Module Timetable
The order in which elements of this Safe Solar Work module training are delivered may vary according to the didactical choices of the delivering training provider.
The delivery of this module must comply with the requirements described in the GWO Requirements for Training
Lesson
Element
Duration
1. Introduction to the training
1.1
Safety instructions and emergency procedures
1.2
Facilities
1.3
Introduction
1.4
Scope and main learning objective
Ongoing assessment (participant performance assessment form)
1.5
1.6
Motivation
1.7
Human factors TOTAL
30 min.
2. Fire Safety Legislation
2.1
National legislation and local guidelines TOTAL
5 min.
3. Fire combustion and fire spread
3.1
Types of fires
3.2
Fire triangle
3.3
Fire spread
3.4
Fire gases TOTAL
20 min.
4. Fire extinguishing
4.1
Contingency plan
4.2
Assessing the fire
4.3
Fire classes TOTAL
25 min.
Global Wind Organisation / www.globalwindsafety.org
58 / 128