L3 Performing a Test

4.6.2 Start a Run Select the START TEST target or press the Start/Stop push button on the test frame to being a test run. NOTE The LED should indicate green prior to you pressing the push button. This indicates ready.

4.6.3 Stop a Run You may stop an active test run by pressing the Start/Stop push button, or by pressing the STOP TEST target on the Controller view.

NOTE An active test run will also stop due to the following:

• Emergency stop switch is pressed • Crosshead travel limit exceeded • Load cell sensor load limit exceeded • Exception event occurred

NOTE During the test run, the LED will blink green indicating that the test frame is active and that the crosshead is moving.

Start Target Press to begin a test run

Stop Target Press to stop a test run