Operations training

High Voltage Standard / V1 02072025

40) Take responsibility for installation environment by removing obstructions and installing necessary supports (e.g., auxiliary winches, guide rollers, chain hooks) (Ability, intermediate level)

41) Recognise safe lifting operations controls and techniques following the lifting plan and WIs, using equipment that is fit for purpose, inspected and certified (Knowledge, basic level)

The instructor shall:

Divide participants into small groups to solve a table-top scenario to prepare equipment for a HV cable pulling operation including:

a.

installing HV cable support

b.

install auxiliary winch

c.

install guide rollers

d. removal of obstructions, platform floor plates, hatchways, etc

e. correct set-up of cable drum (alignment, unrolling from top.

Ask each group to identify steps and requirements for installing HV cable supports, auxiliary winches, and guide rollers.

Quiz participants on relevant preparations such as:

a.

removal of any obstructions

b.

preparing the installation area

c.

focusing on platform floor plates and hatchways.

Allocate participants into group to plan preparations for safe lifting activity

a. introduce participants to a chain and hooking guide (as per company practices)

b.

allocate different lift plans to each group

c. request them to identify the appropriate lifting accessories from plans

Issue a selection of lifting slings to participant groups and have them:

a.

complete pre-use visual inspections

b.

distinguish the load weight capacity