20250702 Solar Technical Training v1

Technical training

Solar Technical Training Standard / V1 02072025

b.

excess cable should not be cut out, but coiled

c. how to bend in accordance with work instructions considering the coil bending radius

d. end protection caps are only to be removed just before the cable is connected to the individual processor

Demonstrate how to perform termination on signal cables:

a.

mounting of ferrules

b.

mounting in clamp and screw terminals

c.

shield termination types

Demonstrate how to perform termination on main power cables (copper/aluminium):

a.

mounting of cable lugs on busbar (correct torque)

b.

mounting of cable to connectors (correct torque)

Facilitate discussions about typical faults during termination

Facilitate practice for the participants to mark, route and terminate all cable types

Give constructive feedback on the participants’ marking, routing and termination of all cable types

The participants shall:

Engage in discussions about typical faults during termination:

a.

insulation in terminal and loose cores

b.

incorrect torque – generates heat

c.

poor crimping – all kinds of scenarios

Practice mounting markings in accordance with an electrical diagram:

a.

cable and conductor

b.

cabinet diagram

Practice routing all cable types applying these factors:

a.

bending radius

b.

distance between cable types and groups