Civil Structural Brochure LH 2025

Shell Creek Bulkhead Rehabilitation Town of Hempstead Department of Parks & Recreation

The existing 1,750 ft long steel bulkhead protecting the shoreline of Shell Creek Park showed signs of deterioration after 40 years of service. LiRo-Hill performed a survey to determine the extent of the damage. Test pits exposed the existing tie rods and deadmen for inspection. Although areas of the steel pile had lost section, it was determined that the bulkhead could be refaced and that a complete replacement would not be required. A restoration design, incorporating cathodic protection to extend the service life of the steel sheeting, was developed. The project included replacement of the asphalt walkway bordering the bulkhead, a continuous safety railing, and a new gazebo looking out toward Reynolds Channel. Coordination with NYSDEC was required for project approval and permitting.