ELEMENT 7.9 - PRE-USE INSPECTION OF PPE
The instructor shall:
Lead a discussion about the importance of pre-use inspection of PPE prior to transfer Demonstrate how to perform a pre-use inspection of PPE for working at height and transfer including quick connectors
INSTALLATIONS, VESSELS AND WTGS
15 min.
The aim of this lesson is to enable the course participants to act safely onboard installations, vessels and wind turbines during normal operations and in case of emergencies and evacuation through understanding the importance and locations of contingency plans.
To successfully complete this lesson each course participant shall be able to:
Explain the importance of general safety on board (L2 – Knowledge)
Explain where contingency plans on installations, vessels and wind turbines are typically located (L2 – Knowledge)
ELEMENT 8.1 - SAFETY ON BOARD
The instructor shall:
Explain general safety on board installations, vessels and WTGs
Lead a discussion about how can failing to adhere to general safety on board installations, vessels and WTGs lead sea survival situations
ELEMENT 8.2 - CONTINGENCY PLANS
The instructor shall:
Show examples of and explain where contingency plans on installations, vessels and wind turbines are typically located, at a minimum covering:
a. Fire
b. Man overboard
c. Abandon ship