2025-05-02_CoHE_V4

Safety training

Control of Hazardous Energies Standard / V4 02052025

Isolation details (Clear name of the isolation and operation)

Time

Signature

Note:

Time

Signature:

One example could be: Close Valve number 5 off ☐

09:11, 14/12/2021

Jane Doe

Note:

Time:

Signature:

another example could be: Open circuit breaker 123 ☐ Apply Lockout-Tagout ☐ Test for absence of voltage ☐

09:18, 14/12/2021

Jane Doe

Time:

Signature:

Time:

Signature:

Time:

Signature:

Time:

Signature:

Time:

Signature:

Permit issued:

Do you confirm that all the above isolations have been carried out and a safe work condition has been established? ☐ Do you confirm that the following elements are fully available / implemented? ☐ • All equipment shut down by normal stopping procedures

All energy sources isolated

• All energy isolating equipment "locked out" with adequate lockout devices

All energy isolating equipment tagged

• All potentially hazardous sources or residual energy purged or dissipated

Verification of effectiveness of the isolations

Adequate rescue means available

• All personnel affected by machine/equipment shutdown notified