Operations training
Slinger Signaller Standard / V4 2023-05-02
GOOD PRACTICE: Remember the job is not finished until the clear up is done! Always clear away the lifting tackle, lifting gear, load bearers and dunnage after use. PRECAUTIONS: If you are unsure of the correct lifting or slinging method then see your Lift Controller (CP). The lift supervisor shall act as overall supervisor for this basic auxiliary lift and monitoring the associated TRA 01 for compliance. Do not attempt the lift if you are uncertain of your ability to complete it safely without risk to yourself and others.
BASIC LIFTING PLAN Location
Wind Jackup - Wind Farm 1
Area
starboard side
Permit No.:
WJ-001
Risk Assessment
TRA 01 Below
Lifting Plan No.:
WIND JACKUP 001
Task Details (Step By Step) Yes
Is Diagram/Sketch of Lifting Operation Enclosed? Yes Description Of Lifting Operation: lift one generator off CTV to deck of Wind Jackup at Wind Farm 1. Lifting Equipment to be used for lift: X1 4.75T Shackle X1 WLL 5T - EWL 5M Round Sling
ACTUAL – Generator Atlas Copco QAS 20
Weight of Load:
<900Kg
All lifting operations require the following to be considered at minimum.
Global Wind Organisation©2023 / www.globalwindsafety.org
49 / 73