Operations training
Slinger Signaller Standard / V4 2023-05-02
Steps taken to eliminate danger to personnel involved and others, including barriers where appropriate: Inform any personnel working in the area that a lift will be carried out from CTV to vessel and ask them to vacate the lift area until the lift is complete.
• Deck barriered off, only people involved with slinging inside barrier.
• Slinger to use agreed hand signals to the crane driver.
• Radio communication can be used for more information when craning to the vessel.
• Vessel to be pushed on to j-tubes of the wind.
• Jackup to maintain a stable position during lift.
• Taglines to be used to control load whilst in the air.
• All lifting gear are within current test date and conduct pre-use checks.
• No one to be under suspended load or near any pinch/crush points. Planned by: Signature:
Date:
Reviewed by:
Signature:
Date:
Sample Lift Plan for the Lift Positioning of a Shipping Container in the UK
XXXXX
CLIENT
XXXXX
SITE
XXXXX
PROJECT
XXXXX
Site Address
XXXXX
Site Contact: Phone: email:
XXXXX
Competent Person: Phone: Email:
Global Wind Organisation©2023 / www.globalwindsafety.org
51 / 73
Made with FlippingBook Annual report maker