Basic Technical Training Standard / V9 2024-06-24

Instructions: Each team should conduct a pre-task briefing where they fill out sections 2 (Planning) and 3 (Doing) of this document

Section 2: Planning 2.1 Outline the work procedure and how you intend to complete it:

2.2 Identify critical steps and how you will manage these:

2.3 Identify risks, hazards and control measures in relation to the task:

2.4 Discuss how to reduce the risk of human errors in relation to the task:

Section 3: Doing 3.1 Outline how the team will monitor and control hazards during the task:

3.2 Outline how the team will pause to discuss and check the teams understanding of any deviations

3.3 Identify how team members will retain focus during the repetitive bolt tightening task:

3.4 Outline how the team will conduct self-checking and peer review throughout the task:

Global Wind Organisation / www.globalwindsafety.org