Case Study - Flare Projects (9)

FLARE PROJECTS

Project Design of temporary lifting davit to replace a flare tip offshore

Project Flare stack inspection and flare tip replacement

Project Offshore flare tip replacement

Client Shell FPSO Location North Sea

Client BP Chemicals Location Saltend, Hull

Client Noble Energy

Location Equatorial Guinea

Shell appointed Zenith to design and install a temporary lifting davit, to facilitate the replacement of a 710 kg flare tip on Shell’s FPSO Curlew located in the North Sea.

Zenith completed the inspection and refurbishment on the A5 complex and K1 Ammonia plant. The scope required a combination of access methods, including rope access and suspended cradle access systems.

The 2020 outage work scope included the removal and replacement of the existing flare tip, the flare tip is located on an elevated boom structure. Zenith designed and fabricated a bespoke temporary lifting frame for installation to the existing upper flare derrick to allow the removal of the existing flare tip and the installation of the replacement flare tip (2267 kg).