Planned Timeline 2026

Phases & Major Capital Projects

% of Costs

2037

Phase 1: Site Prep & Earthwork Planning, Raise ground 66’

2026 - 2029

6%

Phase 2: Infrastructure & Utilities Water, Sewer, Electrical, Transit Infra

2029 - 2034

33%

Phase 3: Parks & Placemaking Perm. Structures, Terminal, Parks

2029 - 2035

43%

Phase 4: Expo Specific Build Community Center, Event Venues, Lodging

2033 - 2035

13%

Phase 5: Post Expo Transition Site Conversions, Infra Reset

2035 - 2037

5%

New Navy Conveyance (2028)