Notes to the Consolidated Financial Statements (unaudited)
6. Property, Plant and Equipment
Capital Assets
Construction in Progress
(millions)
in Service
Total
COST Balance, April 1, 2025 Balance, March 31, 2026
$
4,967 5,321 5,400
$
203 243 291
$
5,170 5,564 5,691
Balance, September 30, 2026
ACCUMULATED DEPRECIATION Balance, April 1, 2025 Balance, March 31, 2026 Balance, September 30, 2026
1,793 1,901 1,963
- - -
1,793 1,901 1,963
CARRYING AMOUNTS Balance, March 31, 2026
$ $
3,420 3,437
$ $
243 291
$ $
3,663 3,728
Balance, September 30, 2026
7. Lease Liability
Leases are recognized as right-of-use assets and corresponding liabilities at the date at which a leased asset is available for use. Payments for short-term leases and leases of low-value assets are expensed on a straight-line basis and excluded from the lease liability.
As at September 30, 2026
As at March 31, 2026
(millions)
Total future minimum lease payments Less: Future finance charges on leases
$
18
$
19
(1)
(1)
Present value of lease liability
17
18
Less: Current portion of lease liability
(6)
(6)
$
11
$
12
As at September 30, 2026
As at March 31, 2026
(millions)
Lease liability, beginning of period
$
18
$
13 11
Net additions
2
Principal repayment of lease liability
(3)
(6)
Lease liability, end of period
$
17
$
18
The weighted average discount rate applied to computer leases and vehicle leases is 4.0 per cent based on the rates implicit in the agreements. The weighted average discount rate applied to building leases is 4.0 per cent based on the Corporation’s incremental borrowing rate.