Project Highlights • new universal change rooms • new barrier-free washrooms and showers • new ramp entry to pool • new viewing area • new entrance and reception area • new meeting room • new elevator • new accessible parking
What’s happening now:
• Structural steel and masonry work near completion • HVAC, plumbing, electrical rough-ins • Sprinkler piping installation • Exterior wall assembly construction • Roof parapet and curb construction • Roofing assembly installation • Pouring of the second floor level
Project Timeline
Spring 2023 • Award of tender • Interior demolition
Summer - Fall 2023 • Exterior construction • Interior construction and finishing
Fall 2024 • All work completed*
*If you’ve ever been involved in a construction project, you know that unexpected challenges often arise. All dates are tentative and subject to change. We appreciate your patience and understanding during this unpredictable time.