PRIORITY THREE - 2023
Priority Road Name
Width Length
Area PCC Repairs AC Repairs Surface Treatment
Cost
3 Tennis Court Dr
19 19 19 19 19 32 19 19 19 19 42 75
561 232 270 370 115 550 238 383 295 45
10,659
60
4,000
Seal Coat Seal Coat Seal Coat Seal Coat Seal Coat Seal Coat Seal Coat Seal Coat Seal Coat Seal Coat Seal Coat Seal Coat
$ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $
17,244.98
969.76
3 Tennis Court Dr Parking
4,408 5,130 7,030 2,185
3 Tennis Court Ln 3 Golf Course Ln
40 60
1,800 3,000
8,678.60 13,696.60 69,318.40 52,442.36 26,299.00 9,294.84 480.70 18,601.42 11,742.50 25,000.00 10,158.29 6,500.00 8,500.00 188.10
3 Golf Course Ln Parking
3 Golf Course Dr
1,835 1,302
58,720 24,738 10,450
360 300 200
12,000 10,000
3 Sunset Dr
3 Periwinkle Dr 3 Orange Tree Ln
4,000 1,600
4,522
60
3 Orange Tree Ln Parking
855
3 Palm Blvd
16,086 22,125
200
750
3 Palm Blvd Parking Lot
2,500
Misc. Costs
Total
253,957.26 $
Inflation
Engineering (PSE)
Construction Inspection
Total
279,115.55 $
Three Year PMP Total
775,399.44 $