CASE STUDY
HSE BioGO® Mobile cGMP Cleanroom Mobile temporary cleanroom facility
Client:
HSE, Cork University Hospital
Location:
Cork, Ireland
Project Size:
40’ Modular Facility / 28m2
Duration:
4 Months
The HSE contracted Ardmac to provide a mobile temporary cleanroom facility to support their existing Pharmacy manufacturing capacity on the Cork University Hospital Campus. Ardmac’s solution was key to the fast-track delivery model required for this project. The facility has been integrated into a larger modular unit where our mobile unit is integral to the process required. The unit was design and commissioned to meet ISO 8 requirements and standards and comprises of the following: • ISO 8 Main Lab • ISO 8 Preparation Room • ISO 8 Ante Room • CNC internal Lobby Also an additional Pass Thru was integrated into the external fabric of the unit to allow for sperate material flow to the wider facility.