2023 recognition The Division received external industry recognition for its high standard work at the 2023 Global Light Rail Awards, receiving highly commended awards for both our Stakeholder Engagement, and our Innovation. In addition, our Project Manager, Hamish Falconer, was recognised in the Rising Star category and Grace Hayward was crowned Project Manager of the Year at the 2023 West Midlands Building the Future Awards.
OUR FOCUS FOR 2024
•
With a strong secure orderbook we expect Urban Division to continue its growth in 2024 when we will build on the fantastic advancements made this year. Commissioning the first phase of WBHE and handing over section 5 of BEE. Delivering works at Wednesbury Depot, Phase 2 of WBHE and section 2 of BEE Delivering embedded rail repairs on the Sheffield Tramway 5-year Project commencing in May ‘24. Safety will remain our #1 priority as we work to maintain our current high standard. Continue promoting low carbon alternatives, and work with key supply chain partners to embed a consistent culture. Continue to proactively retain and recognise talent whilst also responding positively to the feedback received from the recent Dialogue survey
•
•
2023 highlights WOLVERHAMPTON (£35M) •
Entry into service September 2023 Now completing additional items
•
• •
Commercial close out WEDNESBURY DEPOT (£30M) • Commenced enabling works • Agree target cost in 2024 • LINE ONE POWER & OLE (£22M) • Phase 1 complete- small gain share • Awarded phase 2a & 2b = £16m • Additional OLE renewals for 2024 BUY BEFORE YOU BOARD (£3M) • Installing oyster card infrastructure SHEFFIELD (5 years @ £10M / yr) • Polymer and concrete track repairs External & building modifications
•
•
•
Made with FlippingBook interactive PDF creator