Front End Engineering Design (FEED)
ENGIE Fabricom Deliverables (P - Preliminary)
Detailed Design / Project Execution
Concept Study
Feasibility Study
TIC Estimate (accuracy to be confirmed)
±40%
±25%
±10%
Process
(P)
Description of scope of process work
(P)
Design basis
Process flow diagrams (PFDs)
(P)
Mass / energy balance
(P)
(P)
Piping and Instrument Diagrams (P&ID)
(P)
Equipment list
(P)
Process data sheets
(P)
Equipment specifications
(P)
Hazardous Area Classification (HAC)
(P)
(P)
Control and operating philosophy and cause and effect diagram
(P)
Pressure relief and blowdown philosophy and calculation
Mechanical and Piping
(P)
(P)
General specifications
(P)
Detailed specifications (inc. painting, insulation)
3D model and layout
(P)
General arrangements
(P)
Main pipe routes
(P)
Piping layouts Pipe stress analysis
(P)
Isometrics Pipe supports Mechanical equipment specifictions
(P)
Electrical
Consumer list (electrical load schedule)
(P)
(P)
Electrical overall power distribution diagram System studies
(P)
(P)
General specifications
(P)
(P)
Single-line diagram
(P)
(P)
Electrical overall power distribution diagram Equipment layouts
(P)
Cable routing layouts
(P)
(P)
Cable schedule
(P)
(P)
Control and Instrumentation
General specification
(P)
Instrument index
(P)
Instrument data sheets
Instrument specifications
(P)
(P)
System architecture
(P)
Control system user requirement specifications
(P)
Terminal and control room arrangement
Instrument arrangement / plant layout Instrument hook ups (mounting details) Cable block diagram
(P)
Termination and loop diagrams
Civil and Structural
General civil and structural specifications
(P)
Detailed civil and structural specifcations Plot plan
(P)
General arrangement drawings
(P)
(P)
Verification of existing structures and civils
(P)
(P)
Design of foundations / piles / slabs
(P)
Design of pits / super structures
(P)
Design of roads and drainage and utilities
(P)
RC drawings and schedules Civil and structural layout and construction drawings
(P)
(P)
Structural loading diagram and foundation loads
(P)
Design of steelwork
Package Engineering
Define and specify package scope and requirements Vendor evaluation and bid analysis Vendor management and vendor design verification Vendor oversight and factory acceptance
Project Management
Project risk analysis Project execution strategy Project plan
(P)
(P)
Work breakdown structure and cost control
Project organisation chart Document control and approval procedure Project / scope change procedure Hand-over procedure (from construction to commissioning) Take-over procedure (from commissioning to operations) Progress / status reporting
(P)