Consolidated Transportation Program (CTP) FY 2026 to 2031

MARYLAND TRANSPORTATION AUTHORITY

MARYLAND TRANSPORTATION AUTHORITY CAPITAL PROGRAM SUMMARY ($ MILLIONS)

SIX - YEAR TOTAL

FY 2026

FY 2027

FY 2028

FY 2029

FY 2030

FY 2031

Major Construction Program

1,159.4 970.1 176.0

872.3 635.3 166.6 52.7

1,135.9 965.3

1,253.0 1,152.3

1,155.6 1,119.3

504.5 488.9

6,080.5 5,331.2 450.8 237.8

System Preservation Expansion/Efficiency Safety & Security

81.4 69.2

26.7 61.3

-

-

7.6 1.3 4.3 2.3 2.3

31.4

15.6

Environment Administration

0.0

0.0

1.2

-

- - - -

2.6

17.5

20.1

11.4

4.8

58.1

Major Development & Evaluation Program

3.7 3.7

- -

- -

- -

6.0 6.0

Expansion/Efficiency

124.8 104.1

209.0 189.7

434.2 393.6 29.0

553.8 522.4 22.5

571.2 556.4

459.9 437.2 21.0

2,353.0 2,203.3

Minor Program

System Preservation Expansion/Efficiency Safety & Security

3.4

5.6

8.9 5.9

90.5 48.4

10.3

12.5

9.6 2.1

8.4 0.5

1.7

Environment Administration

6.3 0.8

0.9 0.3

- -

- -

9.7 1.1

-

-

Capital Salaries, Wages & Other Costs

-

-

-

-

-

-

-

TOTAL

1,286.5

1,085.0

1,570.2

1,806.8

1,726.8

964.4

8,439.6

Toll Funds

1,286.5

1,085.0

1,570.2

1,806.8

1,726.8

964.4

8,439.6

MARYLAND TRANSPORTATION AUTHORITY -- Line 1

Primary Construction Program

PROJECT: I-95 John F. Kennedy Memorial Highway - Express Toll Lanes (ETL) Northern Extension

DESCRIPTION: The two-lane Express Toll Lane extension to MD 24 includes I-95 safety improvements from Cowenton Road to MD 24; the reconstruction of the MD 24 and MD 152 interchanges; the replacement of four bridges over I-95 (Bradshaw Road, Old Joppa Road, Clayton Road, and Raphel Road); the construction of five noise walls; and environmental mitigation.

PURPOSE & NEED SUMMARY STATEMENT: Traffic operations on northbound I-95 beyond the current MD 43 Express Toll Lanes terminus experience routine congestion during peak hours. The improvements will address capacity concerns, improve safety, and allow for better incident management and maintenance activities. The construction of additional noise walls will address the community's requests about quality of life.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: Enhance Safety and Security X

X X

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

Promote Environmental Stewardship

Deliver System Quality

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: Extending the northbound Express Toll Lanes and associated improvements will provide congestion

PFA Status Yet to Be Determined

Exception Granted

relief and address safety concerns.

STATUS: The extended northbound I-95 Express Toll Lanes (ETL) opened on December 18, 2024, from White Marsh Boulevard (MD 43) to Mountain Road (MD 152). Engineering and construction continue on the extension from Mountain

Road (MD 152) to MD 24.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: Cost decreased by $11 million. The ETL Northbound Extension has received favorable bids for several contracts that have been below cost estimates. These include the last two large contracts in the ETL program. Additionally, the program is moving into its final stages with the first section open to traffic and the final contracts in procurement or construction. Therefore, the decision was made to reduce the overall program budget.

CURRENT YEAR 2026 0 1,773 122 3,093

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025 0 2,302

...2028... ...2029...

...2030...

...2031...

0 511

0 2,313 122 3,093

Planning

0

0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

92,662

90,349

15

13

0

0

0 0

Right-of-way

7,980

7,858

298 196

0

0

0

0

Utility

10,967

7,874

0

0

0

0

98,912 99,423 0 99,423 0

281,951 287,479 0 287,479 0

Construction

927,695

645,744

166,038 168,834 0 168,834 0

122,672 127,660 0 127,660 0

42,305

18,062

0

0

Total

1,039,304

751,825

42,320

18,075

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

1,039,304

751,825

42,320

18,075

0

0

Other

0

0

0

0

0

0

602

PAGE

MDTA--1

MARYLAND TRANSPORTATION AUTHORITY -- Line 2

Primary Construction Program

PROJECT: I-95 John F. Kennedy Memorial Highway - Construct Interchange at Belvidere Road

DESCRIPTION: The project will construct a new interchange between I-95 John F. Kennedy Memorial Highway and Belvidere Road, including constructing a new bridge over I-95.

PURPOSE & NEED SUMMARY STATEMENT: Increased development in the vicinity of Belvidere Road in Cecil County necessitates an interchange at I-95 (JFK Highway) and Belvidere Road. The project cost will be shared with Stewart Properties contributing $8.8 million for right-of-way, Cecil County contributing $1 million for construction, and MDTA providing $46.7 million, with the balance of $20 million from a Federal BUILD Grant. The BUILD Grant was awarded in December 2018. At the time of the grant application in 2018, the project was estimated at $54 million; however, the cost shown on this page reflects the low bid received from the selected Design-Build team.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: Enhance Safety and Security

X Serve Communities and Support the Economy

X Grandfathered

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

X

Promote Environmental Stewardship

Deliver System Quality

Project Inside PFA Project Outside PFA

Exception Will Be Required

EXPLANATION: This project will support development by providing access to I-95 at Belvidere Road.

PFA Status Yet to Be Determined

Exception Granted

STATUS: Engineering is complete. Construction is underway.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026 0 10

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025 0 174

...2028... ...2029...

...2030...

...2031...

0 0 0 0

0 10

Planning

0

0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

6,772

6,762

0

0

0

0

0 0

Right-of-way

0

0

0 0

0 0

0

0

0

0

Utility

0

0

0

0

0

0

8,542 8,542 0 8,542 0

33,424 33,434 0 33,434 0

Construction

74,889

41,465

22,635 22,809 0 22,809 0

22,516 22,526 0 22,526 0

2,366

0

0

0

Total

81,661

48,227

2,366

0

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

81,661

48,227

2,366

0

0

0

Other

0

0

0

0

0

0

2477

PAGE

MDTA--2

MARYLAND TRANSPORTATION AUTHORITY -- Line 3

Primary Construction Program

PROJECT: I-95 John F. Kennedy Memorial Highway - I-95 Southbound Hard Shoulder Running

DESCRIPTION: This project will provide part-time left shoulder use for approximately 5.4 miles on I-95 southbound from Maryland House to MD 24 in Harford County. It involves restriping I-95 and repaving the left shoulder lane to accommodate part-time left shoulder use. Installation of Intelligent Transportation System (ITS) devices to dynamically open and close the left shoulder lane based on traffic conditions is included. This is a Project Labor Agreement candidate project.

PURPOSE & NEED SUMMARY STATEMENT: This project will increase capacity along southbound I-95 between Maryland House and MD 24 and reduce congestion during high traffic volumes. The part time shoulder will be utilized during prescheduled peak periods and during unforeseen spikes in demand.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: X X Enhance Safety and Security Deliver System Quality

X Serve Communities and Support the Economy

X Grandfathered

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

Promote Environmental Stewardship

Project Inside PFA Project Outside PFA

Exception Will Be Required

EXPLANATION: This segment of I-95 currently operates at an unacceptable level of service with significant delays on summer weekends and the Maryland House On-Ramp is a high frequency crash location with approximately 75% of crashes occurring on the weekends. This project will increase capacity and improve safety, particularly during summer weekends, to alleviate severe congestion, delays and crashes along southbound I-95 between the Maryland House and MD 24.

PFA Status Yet to Be Determined

Exception Granted

STATUS: Engineering is underway. Pre-construction activities for BGE Service Requests are underway. Major construction will begin in FY 2027.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026 0 270

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025 0 797

...2028... ...2029...

...2030...

...2031...

0 0 0 0

0 270

Planning

0

0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

3,860

3,590

0

0

0

0

0 0

Right-of-way

0

0

0 0 22 819 0 819 0

0 0

0

0

0

0

Utility

0

0

0

0

0

0

13,723 13,723 0 13,723 0

35,378 35,648 0 35,648 0

Construction

35,400

22

2,384 2,654 0 2,654 0

13,649

5,622

0

0

Total

39,260

3,612

13,649

5,622

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

39,260

3,612

13,649

5,622

0

0

Other

0

0

0

0

0

0

202

PAGE

MDTA--3

MARYLAND TRANSPORTATION AUTHORITY -- Line 4

Primary Construction Program

PROJECT: I-95 John F. Kennedy Memorial Highway - JFK Maintenance Facility Complex

DESCRIPTION: The complex will include a new maintenance building to support office space, common areas, locker/rest rooms, automotive shop/bays, material storage, wash bay, salt storage barns, fueling island, debris dewatering pad, and vehicle storage structures. Site improvements shall include grading, pavement, drainage, utilities, storm water management, lighting, security, fencing, and landscaping. This is a Project Labor Agreement candidate project.

PURPOSE & NEED SUMMARY STATEMENT: The Kennedy Highway and approach roadways require continuous maintenance and safety activities to maintain Kennedy Highway and Hatem Bridge in the highest serviceable condition for safe passage of MDTA customers. The JFK Maintenance Facility Complex will provide work areas for the staff, vehicle safety inspections, and full service repair shop bays and parts storage.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: X X Enhance Safety and Security Deliver System Quality

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

Promote Environmental Stewardship

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: The Maintenance Building will support an environment safe for MDTA employees to perform their

PFA Status Yet to Be Determined

Exception Granted

work duties and protection for the equipment used by operations staff.

STATUS: Engineering and right-of-way acquisition are underway. Construction will begin in FY 2027.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026 0 400 2,750

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025 0 319

...2028... ...2029...

...2030...

...2031...

0 99

0 499 2,750 0

Planning

0

0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

4,025

3,526

0

0

0

0

0 0

Right-of-way

2,750

0

0 0 40 359 0 359 0

0

0

0

0

Utility

0

0

0 0 3,150 0 3,150 0

0

0

0

0

12,807 12,906 0 12,906 0

45,356 48,605 0 48,605 0

Construction

45,431

76

17,006

10,700

4,843

0

Total

52,206

3,602

17,006

10,700

4,843

0

Federal-Aid

0

0

0

0

0

0

TOLL

52,206

3,602

17,006

10,700

4,843

0

Other

0

0

0

0

0

0

2500

PAGE

MDTA--4

MARYLAND TRANSPORTATION AUTHORITY -- Line 5

Primary Construction Program

PROJECT: I-95 John F. Kennedy Memorial Highway - I-695 Ramps to I-95 Northbound Express Toll Lanes DESCRIPTION: Construct two I-95 Section 100 ETL Ramps from I-695 Eastbound and Westbound to I- 95 Northbound ETLs.This is a Project Labor Agreement candidate project.

PURPOSE & NEED SUMMARY STATEMENT: The two ETL ramps are a part of the connectivity between two major interstate roadways and specifically the northbound ETLs. This allows traffic on I-695 a choice to use the NB General Purpose (GP) lanes or the NB ETLs. This improvement will reduce the volume of traffic traveling onto the GP lanes and thereby improves traffic operation on the I-95 facility.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: X X Enhance Safety and Security X Deliver System Quality

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

Promote Environmental Stewardship

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: Once open, these I-695 ramps will provide access to I-95 NB ETLs for a distance of approximately 12

PFA Status Yet to Be Determined

Exception Granted

miles.

STATUS: Engineering and Utility are underway. Construction expected to begin in April 2026.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026 0 1,056 0 100

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025 0 1,199

...2028... ...2029...

...2030...

...2031...

0 0 0 0

0 1,056 0 100

Planning

0

0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

5,425

4,369

0

0

0

0

Right-of-way

0

0

0 0 0 1,199 0 1,199 0

0

0

0

0

Utility

100

0

0

0

0

0

37,700 37,700 0 37,700 0

73,600 74,756 0 74,756 0

Construction

73,600

0

20,750 21,906 0 21,906 0

14,850

300

0

0

Total

79,125

4,369

14,850

300

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

79,125

4,369

14,850

300

0

0

Other

0

0

0

0

0

0

2582

PAGE

MDTA--5

MARYLAND TRANSPORTATION AUTHORITY -- Line 6

Primary Construction Program

PROJECT: I-95 Fort McHenry Tunnel - Rehabilitate Vent Fans

DESCRIPTION: Rehabilitate forty-eight ventilation fans in the Fort McHenry Tunnel East and West Ventilation Buildings.

PURPOSE & NEED SUMMARY STATEMENT: The ventilation system is an integral part of the Fort McHenry Tunnel. Rehabilitating the fans and their components will improve the operational reliability of the existing fans and extend the service life of the ventilation system in the tunnel.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: X X Enhance Safety and Security Deliver System Quality

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

Promote Environmental Stewardship

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: Rehabilitating the fans will extend the useful life of the existing ventilation system.

PFA Status Yet to Be Determined

Exception Granted

STATUS: Open to Service.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026 0 288

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025

...2028... ...2029...

...2030...

...2031...

0 0 0 0 0 0 0 0 0

0 288 0 0 0 288 0 288 0

Planning

0

0

0 0 0 0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

3,149

2,861

0

0

0

0

Right-of-way

0

0

0 0 0 288 0 288 0

0

0

0

0

Utility

0

0

0

0

0

0

Construction

43,178

43,178

1,376 1,376 0 1,376 0

0

0

0

0

Total

46,327

46,039

0

0

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

46,327

46,039

0

0

0

0

Other

0

0

0

0

0

0

2251

PAGE

MDTA--6

MARYLAND TRANSPORTATION AUTHORITY -- Line 7

Primary Construction Program

PROJECT: I-95 Fort McHenry Tunnel - Port Covington I-95 Access Study

DESCRIPTION: The first phase of this project is a comprehensive evaluation of potential improvements to I-95 ramps required to support major planned development on the Port Covington Peninsula located in Baltimore City. Improvements being evaluated include potential changes to the I-95 ramps between Hanover Street and Key Highway.

PURPOSE & NEED SUMMARY STATEMENT: A National Environmental Policy Act (NEPA) study is required to determine the potential environmental effects associated with proposed improvements to accommodate anticipated growth while maintaining the functionality of the regional and local transportation system.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: Enhance Safety and Security X

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

X

Promote Environmental Stewardship

Deliver System Quality

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: The study will identify preferred infrastructure improvements to support the full development potential of a large area of underutilized land in Baltimore City while maintaining the functionality of the regional

PFA Status Yet to Be Determined

Exception Granted

STATUS: Planning is on hold. Construction schedule to be determined. Planning funding will be for MDTA's oversight of the planning phase which is being funded by a private developer. Construction funding will be MDTA's match for future INFRA Grant.

transportation system.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE 20

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025

...2028... ...2029...

...2030...

...2031...

0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0

Planning

409

389

0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0

0

0

0

0

Engineering

6

6

0

0

0

0

0 0 0

Right-of-way

0

0

0

0

0

0

Utility

0

0

0

0

0

0

Construction

32,985

0

0

0

0

0

32,985 33,005 0 33,005 0

Total

33,400

395

0

0

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

33,400

395

0

0

0

0

Other

0

0

0

0

0

0

2442

PAGE

MDTA--7

MARYLAND TRANSPORTATION AUTHORITY -- Line 8

Primary Construction Program

PROJECT: I-95 Fort McHenry Tunnel - Rehabilitate Substructure and Superstructure of Various Bridges on I-95 in Baltimore City DESCRIPTION: Repair substructure and superstructure of seventy-four bridges on I-95 in Baltimore City. The work includes structural weld repairs, structural steel repairs, roadway joint repairs, concrete repairs, and application of protective coatings on seventy-four bridges. This project includes two phases. Each phase includes thirty-seven bridges.

PURPOSE & NEED SUMMARY STATEMENT: The annual facility inspections, as well as findings and issues noted by MDTA Operations, have identified the need to perform a comprehensive substructure and superstructure rehabilitation throughout this facility.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: X X Enhance Safety and Security Deliver System Quality

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

Promote Environmental Stewardship

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: The bridges show signs of deterioration. Rehabilitation will improve condition of the bridges'

PFA Status Yet to Be Determined

Exception Granted

substructure and superstructure.

STATUS: Open to Service.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025

...2028... ...2029...

...2030...

...2031...

0 0 0 0 0 0 0 0 0

0 0 0 0

Planning

0

0

0 0 0 0

0 0 0 0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

4,885

4,885

0

0

0

0

Right-of-way

0

0

0

0

0

0

Utility

0

0

0

0

0

0

200 200 0 200 0

Construction

28,185

27,985

3,202 3,202 0 3,202 0

200 200 0 200 0

0

0

0

0

Total

33,070

32,870

0

0

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

33,070

32,870

0

0

0

0

Other

0

0

0

0

0

0

2397, 2513

PAGE

MDTA--8

MARYLAND TRANSPORTATION AUTHORITY -- Line 9

Primary Construction Program

PROJECT: I-95 Fort McHenry Tunnel - Rehabilitate Tunnel 15 KV Cable, Conduit, and Concrete Wall

DESCRIPTION: The scope of this project includes performing concrete repairs to the underside of the roadway slab and walls inside the fresh air ducts of all four bores of the Fort McHenry Tunnel. In addition, replacement of the existing four (4) 15KV tie feeders, with associated cables and conduits, between the East and West Ventilation Buildings.

PURPOSE & NEED SUMMARY STATEMENT: Hands-on inspections identified the original 15KV cable and conduits including the surrounding concrete need major rehabilitation and replacement.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: X X Enhance Safety and Security Deliver System Quality

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

Promote Environmental Stewardship

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: Rehabilitate 15KV cable, conduit and surrounding concrete wall to increase the useful life of these

PFA Status Yet to Be Determined

Exception Granted

tunnel components.

STATUS: Engineering is complete. Construction is underway.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025

...2028... ...2029...

...2030...

...2031...

0 0 0 0 0 0 0 0 0

0 0 0 0

Planning

0

0

0 0 0 0

0 0 0 0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

476

476

0

0

0

0

Right-of-way

0

0

0

0

0

0

Utility

0

0

0

0

0

0

10,434 10,434 0 10,434 0

Construction

32,808

22,374

5,993 5,993 0 5,993 0

10,434 10,434 0 10,434 0

0

0

0

0

Total

33,284

22,850

0

0

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

33,284

22,850

0

0

0

0

Other

0

0

0

0

0

0

2458

PAGE

MDTA--9

MARYLAND TRANSPORTATION AUTHORITY -- Line 10

Primary Construction Program

PROJECT: I-95 Fort McHenry Tunnel - FMT Facility-wide Zone Paint Program

DESCRIPTION: This is a system preservation project to address areas of structural steel with moderate to advanced section loss and corrosion. The project will provide zone painting to bridges in the areas of higher corrosion to prevent further deterioration.

PURPOSE & NEED SUMMARY STATEMENT: Bridge inspections revealed significant areas of the structural steel with moderate to advanced section loss particularly at the steel beam ends at the locations of open roadway joints.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: Enhance Safety and Security

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

X

Promote Environmental Stewardship

Deliver System Quality

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: The patina protecting the steel is wearing off, therefore cleaning and painting the steel is needed to

PFA Status Yet to Be Determined

Exception Granted

prevent further deterioration.

STATUS: Engineering is complete. Construction is underway.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025

...2028... ...2029...

...2030...

...2031...

0 0 0 0

0 0 0 0

Planning

0

0

0 0 0 0

0 0 0 0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

115

115

0

0

0

0

Right-of-way

0

0

0

0

0

0

Utility

0

0

0

0

0

0

6,113 6,113 0 6,113 0

20,766 20,766 0 20,766 0

Construction

26,424

5,658

5,647 5,647 0 5,647 0

11,843 11,843 0 11,843 0

2,810

0

0

0

Total

26,539

5,773

2,810

0

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

26,539

5,773

2,810

0

0

0

Other

0

0

0

0

0

0

217

PAGE

MDTA--10

MARYLAND TRANSPORTATION AUTHORITY -- Line 11

Primary Construction Program

PROJECT: I-95 Fort McHenry Tunnel - Rehabilitate FMT Area-Wide Lighting

DESCRIPTION: Upgrade portions of the lighting system, electrical system, and camera communication feeds on the Fort McHenry Tunnel facility to bring assets back into operation.

PURPOSE & NEED SUMMARY STATEMENT: This project will upgrade and restore assets back into operation including improvements to lighting, electrical and communication feeds, parapet cables and circuits, lighting vaults and cabinets, junction box covers, and conduit throughout.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: X X Enhance Safety and Security Deliver System Quality

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

Promote Environmental Stewardship

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: Rehabilitation is needed to extend the lifecycle of the assets.

PFA Status Yet to Be Determined

Exception Granted

STATUS: Engineering is complete. Construction is underway.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025

...2028... ...2029...

...2030...

...2031...

0 0 0 0

0 0 0 0

Planning

0

0

0 2 0 0

0 0 0 0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

518

518

0

0

0

0

Right-of-way

0

0

0

0

0

0

Utility

0

0

0

0

0

0

4,957 4,957 0 4,957 0

10,524 10,524 0 10,524 0

Construction

10,817

293

293 295 0 295 0

4,260 4,260 0 4,260 0

1,307

0

0

0

Total

11,335

811

1,307

0

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

11,335

811

1,307

0

0

0

Other

0

0

0

0

0

0

200

PAGE

MDTA--11

MARYLAND TRANSPORTATION AUTHORITY -- Line 12

Primary Construction Program

PROJECT: I-95 Fort McHenry Tunnel - FMT Box Girder Preservation

DESCRIPTION: Clean, paint, and repair deteriorated portions of the FMT box girders, especially the supporting girder ends. Multiple bridges on the FMT facility are supported by hollow girders rectangular or "box" in cross section rather than normal "I" shaped girders. These box girders span multiple support piers spaced along their lengths. The work in this project is to abrasive blast (clean) and paint the areas of steel that are rusted inside and outside the girders.

PURPOSE & NEED SUMMARY STATEMENT: The purpose of this project is to remove rust and associated steel deterioration in areas of the FMT "Box" girders by cleaning and painting the rusted steel areas, discovered during biennial inspections, to preserve the useful life of these girders.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: Enhance Safety and Security

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

X

Promote Environmental Stewardship

Deliver System Quality

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: Cleaning and painting the box girders will preserve and extend their useful life.

PFA Status Yet to Be Determined

Exception Granted

STATUS: Engineering is complete. Construction is expected to begin in April 2026.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026 0 31

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025 0 39

...2028... ...2029...

...2030...

...2031...

0 0 0 0

0 31

Planning

0

0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

500

469

0

0

0

0

0 0 9,996 10,027 0 10,027 0

Right-of-way

0

0

0 0 0 39 0 39 0

0 0

0

0

0

0

Utility

0

0

0

0

0

0

4,998 4,998 0 4,998 0

Construction

9,996

0

833 864 0 864 0

4,165

0

0

0

Total

10,496

469

4,165

0

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

10,496

469

4,165

0

0

0

Other

0

0

0

0

0

0

2580

PAGE

MDTA--12

MARYLAND TRANSPORTATION AUTHORITY -- Line 13

Primary Construction Program

PROJECT: I-95 Fort McHenry Tunnel - MDTA Police Vehicle Storage Garage and Auto Repair Shop

DESCRIPTION: Project to construct a new multi-use facility at the Fort McHenry Tunnel Campus to support the MDTA police vehicle fleet. The building will include four (4) storage bays for safe shelter of various essential vehicles and equipment including the Command Vehicle and Motorcycles. The Automotive Service Shop will have three (3) bays to provide maintenance and repair for MDTA police vehicles along with office, support and parts storage space.

PURPOSE & NEED SUMMARY STATEMENT: MDTA Police identified the necessity for a centralized facility to support storage of essential vehicles for emergency response and expansion of the patrol fleet. The police vehicle fleet will increase by approximately 175 vehicles over the next two years. These emergency response vehicles require more frequent and stringent safety inspections. The existing facility auto shops will not have the capacity to perform inspections, routine maintenance, and repairs for the increased fleet due to the total number of vehicles both new and existing. The current auto shops service the entire MDTA maintenance vehicle and heavy equipment fleet.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: Enhance Safety and Security

X Serve Communities and Support the Economy

X

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

Promote Environmental Stewardship

Deliver System Quality

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: Provide a more suitable centralized location for safe and efficient management of the MDTA police vehicle fleet.

PFA Status Yet to Be Determined

Exception Granted

STATUS: Engineering is underway. Construction to begin in FY 2027.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026 0 1,061

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025 0 439

...2028... ...2029...

...2030...

...2031...

0 0 0 0

0 1,061

Planning

0

0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

2,473

1,412

0

0

0

0

0 0

Right-of-way

0

0

0 0 0 439 0 439 0

0 0 0 1,061 0 1,061 0

0

0

0

0

Utility

0

0

0

0

0

0

7,125 7,125 0 7,125 0

21,015 22,076 0 22,076 0

Construction

21,015

0

7,536

6,354

0

0

Total

23,488

1,412

7,536

6,354

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

23,488

1,412

7,536

6,354

0

0

Other

0

0

0

0

0

0

2499

PAGE

MDTA--13

MARYLAND TRANSPORTATION AUTHORITY -- Line 14

Primary Construction Program

PROJECT: I-695 Francis Scott Key Bridge - Key Bridge Rebuild

DESCRIPTION: This project will replace the Francis Scott Key Bridge and approaches using a Progressive Design-Build procurement process. The project is expected to be funded from insurance and FHWA emergency relief proceeds. Regionally, the Key Bridge played a critical role in the transportation network, including the transport of goods to and from the Port of Baltimore, the nation’s largest port facility for specialized cargo and passenger facilities, and nearby distribution centers such as Tradepoint Atlantic at Sparrows Point. On 12/21/24, Congress approved the full federal funding of the Key Bridge Replacement Project’s eligible costs. The MDTA will use toll revenue to fund the up front costs of the Key Bridge reconstruction, with Federal reimbursement in the future.

PURPOSE & NEED SUMMARY STATEMENT: On March 26, 2024, a cargo container vessel struck a main pier of the Francis Scott Key Bridge while transiting out of the Baltimore Harbor. The impact caused the bridge to collapse into the Patapsco River within seconds of the allision. As a result, the I- 695 highway and ship channel became impassable. The loss of the Francis Scott Key Bridge significantly impacts travel in the Baltimore Metropolitan Region. The preliminary design phase is being delivered using an aggressive schedule, so construction can commence as soon as possible.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: X X Enhance Safety and Security Deliver System Quality

X X Serve Communities and Support the Economy Promote Environmental Stewardship

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: Replacing the Francis Scott Key Bridge will restore critically affected traffic patterns in the Baltimore Metropolitan Region. It is a critical link in the regional and interstate transportation network and was the primary interstate route for hazardous material loads traveling through Baltimore. The collapse has negatively impacted community mobility and connectivity by creating a major gap in the Baltimore transportation network for both local and regional traffic.

PFA Status Yet to Be Determined

Exception Granted

STATUS: Planning, engineering and construction are underway.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: Cost increased by $3.4 billion due to detailed design development and refinement, as well as detailed cost estimating efforts. Previous cost estimates were developed for programming purposes shortly after the Key Bridge collapse.

CURRENT YEAR 2026 1,733 115,325

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025 91 77,742

...2028... ...2029...

...2030...

...2031...

0 0 0 0

1,733 115,325

Planning

2,000

267

0

0

0

0

0 0 0 0

Engineering

193,179

77,854

0

0

0

0

0 0

Right-of-way

0

0

0 0 1,264 79,098 0 79,098 0

0 0

0

0

0

0

Utility

0

0

0

0

0

0

529,583 529,583 0 529,583 0

4,874,309 4,991,367 0 4,991,367 0

Construction

4,993,579

1,968

719,432 836,490 0 836,490 0

896,359 1,128,859

1,112,560

487,517

117,302 117,302 0 117,302 0

Total

5,188,758

80,088

896,359 1,128,859

1,112,560

487,517

Federal-Aid

0

0

0

0

0

0

TOLL

5,188,758

80,088

896,359 1,128,859

1,112,560

487,517

Other

0

0

0

0

0

0

2655

PAGE

MDTA--14

MARYLAND TRANSPORTATION AUTHORITY -- Line 15

Primary Construction Program

PROJECT: I-695 Francis Scott Key Bridge - Subgrade Improvements at Bear Creek

DESCRIPTION: This project will rehabilitate the subgrade and pavement systems of the I-695 roadway in the Bear Creek vicinity.

PURPOSE & NEED SUMMARY STATEMENT: The purpose of the project is to repair and rehabilitate the subgrade and pavement of MD 695 near Bear Creek and perform backwall repairs of adjacent bridges. The need for repairs and rehabilitation are based on studies that revealed settlement and deterioration in this area. The expected increase in truck volumes due to the ongoing development and expansion of Tradepoint Atlantic confirms the need for the rehabilitation at this time.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: Enhance Safety and Security X

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

X

Promote Environmental Stewardship

Deliver System Quality

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: The rehabilitation and repairs of the roadway and bridge abutments will provide a safer and

PFA Status Yet to Be Determined

Exception Granted

smoother ride.

STATUS: Engineering is complete. Construction is underway.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025

...2028... ...2029...

...2030...

...2031...

0 0 0 0

0 0 0 0

Planning

0

0

0 1 0 0

0 0 0 0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

3,721

3,721

0

0

0

0

Right-of-way

0

0

0

0

0

0

Utility

0

0

0

0

0

0

2,564 2,564 0 2,564 0

13,623 13,623 0 13,623 0

Construction

40,192

26,569

20,239 20,240 0 20,240 0

11,059 11,059 0 11,059 0

0

0

0

0

Total

43,913

30,290

0

0

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

43,913

30,290

0

0

0

0

Other

0

0

0

0

0

0

2450

PAGE

MDTA--15

MARYLAND TRANSPORTATION AUTHORITY -- Line 16

Primary Construction Program

PROJECT: I-695 Francis Scott Key Bridge - MDTA Police Training Academy

DESCRIPTION: Construct MDTA Police Training Academy at former Allied Property.

PURPOSE & NEED SUMMARY STATEMENT: There is insufficient space at the Police Headquarters Building, where the Police Training Academy is currently located, due to the growth of police duties and responsibilities over the past decade. There is a consistent and increasing need for new recruit training and in-service accreditation from MDTA Police and other law enforcement agencies that train alongside the MDTA.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: Enhance Safety and Security X

X

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

Promote Environmental Stewardship

Deliver System Quality

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: Construct an independent police training academy building and facility.

PFA Status Yet to Be Determined

Exception Granted

STATUS: Phase 1 is complete. Engineering for Phase 2 is underway. Construction for Phase 2 to begin in FY 2027.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026 0 200

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025 0 147

...2028... ...2029...

...2030...

...2031...

0 16

0 216

Planning

0

0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

2,126

1,910

0

0

0

0

0 0

0 0

Right-of-way

0

0

0 0 0 147 0 147 0

0 0 0 200 0 200 0

0

0

0

0

Utility

0

0

0

0

0

0

7,265 7,282 0 7,282 0

19,413 19,630 0 19,630 0

Construction

22,278

2,865

8,215

3,933

0

0

Total

24,405

4,775

8,215

3,933

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

24,405

4,775

8,215

3,933

0

0

Other

0

0

0

0

0

0

2521

PAGE

MDTA--16

Page 1 Page 2 Page 3 Page 4 Page 5 Page 6 Page 7 Page 8 Page 9 Page 10 Page 11 Page 12 Page 13 Page 14 Page 15 Page 16 Page 17 Page 18 Page 19 Page 20 Page 21 Page 22 Page 23 Page 24 Page 25 Page 26 Page 27 Page 28 Page 29 Page 30 Page 31 Page 32 Page 33 Page 34 Page 35 Page 36

Made with FlippingBook Digital Proposal Creator