Consolidated Transportation Program (CTP) FY 2026 to 2031

MARYLAND TRANSPORTATION AUTHORITY -- Line 20

Primary Construction Program

PROJECT: I-895 Baltimore Harbor Tunnel Thruway - AET Conversion with Frankfurst Avenue Interchange Modifications DESCRIPTION: Demolish toll plaza, rehabilitate pavement, and install equipment to convert to all electronic tolling (AET), or cashless tolling. Modify the I-895 interchange at Frankfurst Avenue to improve safety and operations. The project will be completed in three phases: AET Conversion with Frankfurst Interchange (Gantry Work); Reconstruction Frankfurst Intersection; and I-895 Mainline & Bridge Replacement. This is a Project Labor Agreement candidate project.

PURPOSE & NEED SUMMARY STATEMENT: The advantages of converting to cashless tolling include reduced travel times; increased safety/reduced crashes; alignment with national practice; improved customer convenience; reduced emissions; and reduction in toll collection and maintenance costs. The I-895 interchange modifications will address aging bridges, clearances, and other safety and efficiency related items.

STATE GOALS : Maryland Transportation Plan (MTP) Goals/Selection Criteria: X X Enhance Safety and Security X Deliver System Quality

Serve Communities and Support the Economy

X

SMART GROWTH STATUS:

Project Not Location Specific

Not Subject to PFA Law

Promote Environmental Stewardship

Project Inside PFA Project Outside PFA

Grandfathered

Exception Will Be Required

EXPLANATION: Changing to cashless tolling at the Baltimore Harbor Tunnel provides toll collection at highway

PFA Status Yet to Be Determined

Exception Granted

speeds through the electronic methods of E-ZPass, Pay-By-Plate, and Video Tolling.

STATUS: Design and construction are underway. Only those portions of the construction that can be completed without major traffic impacts are underway at this time due to the increased traffic in this corridor from the Key Bridge corridor closure. The project was awarded an $80M MEGA grant, which will be applied to the construction. Additional funding for the balance of the project will be added later.

SPECIAL

FEDERAL

OTHER

X

GENERAL

POTENTIAL FUNDING SOURCE:

TOTAL

SIGNIFICANT CHANGE FROM FY 2025 - 30 CTP: None.

CURRENT YEAR 2026 0 1,655

BUDGET YEAR 2027

PLANNING FOR PLANNING PURPOSES ONLY

SIX YEAR TOTAL

BALANCE TO COMPLETE

PHASE

ESTIMATED EXPENDED COST THRU ($000) CLOSE YEAR

PREVIOUS YEAR 2025 0 991

...2028... ...2029...

...2030...

...2031...

0 375 0 0 0 375 0 375 0

0 2,030

Planning

0

0

0

0

0

0

0 0 0 0 0 0 0 0 0

Engineering

8,294

6,264

0

0

0

0

0 0

Right-of-way

0

0

0 0

0 0

0

0

0

0

Utility

0

0

0

0

0

0

3,593 5,623 0 5,623 0

Construction

6,800

3,207

2,739 3,730 0 3,730 0

3,593 5,248 0 5,248 0

0

0

0

0

Total

15,094

9,471

0

0

0

0

Federal-Aid

0

0

0

0

0

0

TOLL

15,094

9,471

0

0

0

0

Other

0

0

0

0

0

0

2487